Inspections for the day of: Monday, July 2, 2001.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDave Hannah
TitleBLD-COM/RES INSPECTOR
Phone #794-1967
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-00332 BLD-Aging Inspection7/2/20017/2/20017/2/2001 12:00:00 AM PART
work in progress 7/2/2001 3:59:08 PM
BLD01-00818 BLD-Aging Inspection7/2/20017/2/20017/2/2001 12:00:00 AM PASS
done with out inspection 7/2/2001 2:30:52 PM
MEC01-01918 Final6/29/20017/2/20017/2/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/29/2001 at 13:03:11. Contact: ###-####. 7/2/2001 10:08:51 AM
BLD01-01068 BLD-Footing6/29/20017/2/20017/2/2001 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 06/29/2001 at 13:19:06. Contact: ###-####. work in progress 7/2/2001 10:10:37 AM
MEC01-01268 Final6/29/20017/2/20017/2/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/29/2001 at 15:00:02. Contact: ###-####. fans not working or are not installed 7/2/2001 10:40:55 AM
MEC01-01692 Rough-in6/29/20017/2/20017/2/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/29/2001 at 16:20:02. Contact: ###-####.
MEC01-01692 Pressure Test6/29/20017/2/20017/2/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 06/29/2001 at 16:20:32. Contact: ###-####.
BLD01-00216 BLD-Framing/Rough-in6/29/20017/2/20017/2/2001 12:00:00 AMAPASS
###-#### ok to cover 7/2/2001 10:16:10 AM
BLD01-01574 BLD-Foundation7/2/20017/2/20017/2/2001 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 07/02/2001 at 06:28:37. Contact: ###-####. work in progress 7/2/2001 10:11:02 AM
BLD01-00912 BLD-Framing/Rough-in7/2/20017/2/20017/2/2001 12:00:00 AMPFAIL
shear nailing Dean ###-#### nailing was covered by a rap we cut baak several locations nailing was not quit there told dean to add one more 8 every 12 inches 7/2/2001 3:52:13 PM
BLD01-00173 BLD-Framing/Rough-in7/2/20017/2/20017/2/2001 12:00:00 AMPPASS
Miles ###-####
BLD01-01188 BLD-Footing7/2/20017/2/20017/2/2001 12:00:00 AMPPART
travis ###-####
BLD01-01186 BLD-Footing7/2/20017/2/20017/2/2001 12:00:00 AMPPART
###-####
BLD01-01187 BLD-Footing7/2/20017/2/20017/2/2001 12:00:00 AMPPART
###-#### checked setbacks look ok to north and east prop lines work in progress crew will clean out ftgs 7/2/2001 4:25:04 PM
BLD01-01189 BLD-Footing7/2/20017/2/20017/2/2001 12:00:00 AMPPART
###-####