Inspections for the day of: Monday, July 2, 2012.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD11-01268 FIRE-Final Inspection7/2/20127/2/20127/2/2012 3:46:28 PMPCANC
Area "B" 3rd and 4th floors life safety will be a pass when the project related fire alarm system for this area is tested. Smoke alarms tested.
BLD11-01267 FIRE-Final Inspection7/2/20127/2/20127/2/2012 3:28:44 PMAFAIL
Area "A" 3rd and 4th floors life safety will be a pass when the project related fire alarm system for this area is tested. Smoke alarms tested.
FIR11-00621 INSP-Final Inspection7/2/20127/2/20127/2/2012 3:14:50 PMPPASS
Permit finaled
FIR12-00262 INSP-Sprinkler Rough-in7/2/20127/2/20127/2/2012 3:13:07 PMPPART
Sprinkler piping is ok to cover. One pendant was adjusted while I was there. Sprinkler coverage needs to be provided in the empty tenant space along the new demising wall.
FIR12-00223 INSP-Sprinkler Rough-in/Hydro7/2/20127/2/20127/2/2012 3:11:24 PMPPART
Hydro test passed. Sprinkler piping above the lay-in ceiling tile is ok to cover. Plans and hydraulic calculations need to be resubmitted showing the 1 1/4" far main. The plans and calculations show the piping as 1 1/2" piping. Need the pressure relief valve installed.