BLD03-02718
| FIRE-Final Inspection | 7/19/2004 | 7/20/2004 | 7/20/2004 12:00:00 AM | A | FAIL |
|
|
Provide one more fire extinguisher at the west end of the building and provide building address on exterior 7/20/2004 10:43:39 AM
|
FIR04-00383
| INSP-Conference | 7/20/2004 | 7/20/2004 | 7/20/2004 12:00:00 AM | P | DONE |
|
|
I stopped at the project to discuss with the project manager, Cameron, about the non use of the gymnasium (FIR02-00070). After looking around I found that work is being done in the kitchen area. This work has been permitted through a BLD. But the fire alarm that has been installed in the kitchen and gymnasium areas has not been permitted yet. The work I observed is conduit and wiring to the speaker/strobes in the gym. Wire to a duct detector on zone 6 and fire alarm wiring to the type 1 hood suppression system. Per Rand with Alarm Star he is not the installing contractor. He is unsure who the installing electrician is since they are being hired through the general contractor. Rand did state that Lynn Proctor Electric, in Caldwell, is the onsite electrician and may be the responsible party. I told both Rand and Cameron that all work on the fire alarm system is to stop until approved plans are on site. I contacted Mary in plan review about this issue.
|
BLD04-00868
| FIRE-Final Inspection | 7/20/2004 | 7/20/2004 | 7/20/2004 12:00:00 AM | P | PASS |
|
|
Fire life safety finaled 7/20/2004 4:17:31 PM
|
FIR04-00339
| INSP-Final Inspection | 7/19/2004 | 7/20/2004 | 7/20/2004 12:00:00 AM | P | PASS |
|
|
Fire alarm finaled 7/20/2004 4:01:55 PM
|