FIR10-00583
| INSP-Sprinkler Rough-in/Hydro | 7/20/2011 | 7/20/2011 | 7/20/2011 3:48:25 PM | P | PASS |
|
|
Above ground hydro test passed.
|
FIR11-00299
| INSP-Sprinkler Rough-in | 7/19/2011 | 7/20/2011 | 7/20/2011 2:50:14 PM | P | PASS |
|
|
See the city approved plans for the portion of the 4" and 2 1/2" mains where the rough-in has passed. More new piping has been installed than what is shone on the plans . Per Mike this additional piping will be shown on the new submittals.
|
FIR11-00305
| INSP-Sprinkler Rough-in | 7/19/2011 | 7/20/2011 | 7/20/2011 2:42:26 PM | A | PASS |
|
|
The underground supply piping is ok to cover.
|