FIR16-00239
| INSP-Sprinkler Rough-in | 7/20/2016 | 7/20/2016 | 7/20/2016 2:32:09 PM | P | PASS |
|
|
See the city approved plans for location dated for today where piping can be covered. I noted wood above the ceiling but the wall contractor provided verification that the wood is fire treated.
|
FIR16-00131
| INSP-Final Inspection | 7/20/2016 | 7/20/2016 | 7/20/2016 2:28:39 PM | P | PASS |
|
|
Permit finaled
|
FIR16-00122
| INSP-Final Inspection | 7/20/2016 | 7/20/2016 | 7/20/2016 2:27:18 PM | P | FAIL |
|
|
Resubmit plans (atleast contact plan review) showing all changes which include pump room device layout changes and communication set up that does not match plans, Provide secure box for Dialer transformer, Provide correct labels for the dedicated circuits for the FACP and Bell, Switch addresses for points 42 and 43, Repair strob in Breakroom, Verify Protecto wire temp, Verify compliance with approval notes 1 through 10 (It appears note #1 is not being met). Need to verify signals with written report as discussed. See the city approved plans for devices tested marked "ok"
|
BLD15-02284
| FIRE-Final Inspection | 7/19/2016 | 7/20/2016 | 7/20/2016 9:51:29 AM | A | PASS |
|
|
Life safety passed
|