BLD05-00660
| FIRE-Conference | 7/20/2005 | 7/21/2005 | 7/21/2005 4:35:19 PM | P | FAIL |
|
|
Inspection was for flame retardant that is to be applied to the concealed combustibles above the canopy ceilings. I could not tell if the retardant had been applied or not. Contractor will apply some to a small piece for closer inspection
|
FIR05-00136
| INSP-Final Inspection | 7/20/2005 | 7/21/2005 | 7/21/2005 4:26:06 PM | P | PASS |
|
|
permit finaled
|
FIR05-00068
| INSP-Sprinkler Rough-in/Hydro | 7/21/2005 | 7/21/2005 | 7/21/2005 4:06:40 PM | P | PART |
|
|
Hanger dificiencies as marked on the last edition of the approved have been corrected but the latest revision of the plans was not on site.
|
FIR05-00375
| INSP-Final Inspection | 7/21/2005 | 7/21/2005 | 7/21/2005 2:25:24 PM | P | FAIL |
|
|
Sprinkler piping is ok to cover. Can't give final since tile is missing at the pendant heads.
|
FIR05-00333
| INSP-Sprinkler Rough-in/Hydro | 7/21/2005 | 7/21/2005 | 7/21/2005 1:09:56 PM | P | PART |
|
|
Hydro test and sprinkler rough-in passed. Piping is ok to cover. Need to complete demo work as shown on plans prior to finaling permit.
|
BLD05-00747
| FIRE-Final Inspection | 7/20/2005 | 7/21/2005 | 7/21/2005 12:07:17 PM | A | FAIL |
|
|
Door hardware does not release in a single motion, test exit lights in the presence of the fire inspector. Provide suite number.
|
FIR05-00323
| INSP-Final Inspection | 7/20/2005 | 7/21/2005 | 7/21/2005 10:37:14 AM | A | PASS |
|
|
Permit finaled
|
FIR05-00324
| INSP-Final Inspection | 7/20/2005 | 7/21/2005 | 7/21/2005 10:36:36 AM | A | PART |
|
|
A temporary occupancy was given until the existing audio devices that sound a siren type signal have been changed to temporal signal
|