Inspections for the day of: Friday, July 21, 2006.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00255 INSP-Final Inspection7/20/20067/21/20067/21/2006 3:49:49 PMAFAIL
Inspection was not for a final but for a cover inspection for the hard lid areas. These areas are ok to cover.
FIR06-00452 INSP-Sprinkler Rough-in7/20/20067/21/20067/21/2006 2:57:54 PMAPASS
See marked plans for more areas that the sprinkler piping is ok to cover.
FIR06-00259 FIR-Aging Inspection7/21/20067/21/20067/21/2006 2:48:10 PM NR
Per Greg the work is in progress.
BLD05-03072 FIRE-Final Inspection7/21/20067/21/20067/21/2006 2:43:07 PMPFAIL
Still need the fire alarm permit finaled. Life safety for the shell and Sign Company tenant is ok for a temporary occupancy once the fire alarm is a go. The south tenant work is ongoing at this time.
BLD05-03243 FIRE-Final Inspection7/21/20067/21/20067/21/2006 2:42:48 PMPFAIL
Still need the fire alarm permit finaled. Life safety for the shell and Sign Company tenant is ok for a temporary occupancy once the fire alarm is a go. The south tenant work is ongoing at this time.
BLD05-01262 FIRE-Final Inspection7/21/20067/21/20067/21/2006 2:42:29 PMPFAIL
Still need the fire alarm permit finaled. Life safety for the shell and Sign Company tenant is ok for a temporary occupancy once the fire alarm is a go. The south tenant work is ongoing at this time.
FIR06-00218 INSP-Final Inspection7/20/20067/21/20067/21/2006 2:40:56 PMAFAIL
Still need to hydro test the FDC and connect/test the alarms. Forward flush passed. The rough-in for the south tenant failed due to numerous obstructions to the upright sprinkler heads by duct work.
MIS06-00170 FIR-Final7/21/20067/21/20067/21/2006 1:22:01 PMPPART
A temporary occupancy was given until the fire extinguisher is mounted and tagged as discussed. Provide battery backup for the exit signs and remount the address. Per Ron Hill this was reviewed under the UBC and the occupant load does not require emergency lighting to be installed.
FIR06-00218 INSP-Sprinkler Rough-in/Hydro7/20/20067/21/20067/21/2006 12:40:33 PMAPASS
Above ground hydro test passed. Still need to hydro the remote FDC.
MIS06-00176 FIR-Final7/20/20067/21/20067/21/2006 12:39:41 PMAPASS
Life safety finaled
MIS06-00184 FIR-Final7/20/20067/21/20067/21/2006 9:52:25 AMAFAIL
Repair exit signs, repair emergency lights, mount and tag fire extinguishers and provide annual inspection for the fire sprinkler riser
BLD06-00531 FIRE-Final Inspection7/20/20067/21/20067/21/2006 8:58:20 AMAFAIL
Provide the correct sticker for the door, provide the additional exit sign and exit discharge lighting as noted on the approved plans
BLD05-03475 FIRE-Final Inspection7/20/20067/21/20067/21/2006 8:56:20 AMAPASS
Fire life safety for the shell is passed.
FIR06-00452 INSP-Sprinkler Rough-in7/19/20067/21/20067/19/2006 4:32:59 PMACANC
Mike is the contact @ ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Trent Bice Inspection cancelled from web by: Trent Bice