ELE08-02007
| Electrical Rough-In | 7/21/2008 | 7/21/2008 | 7/21/2008 3:58:07 PM | P | PASS |
|
|
shawn Note:please call 1/2 hr prior to inspection Phone #: ###-#### ric ok, no esc this project
|
ELE08-01989
| Permanent Service | 7/21/2008 | 7/21/2008 | 7/21/2008 3:04:28 PM | P | PASS |
|
|
kieth Phone #: ###-#### p/s o/h rec ok, will call for final, no esc this project
|
ELE08-01508
| Electrical Rough-In | 7/20/2008 | 7/21/2008 | 7/21/2008 2:49:58 PM | P | PART |
|
|
This is for the last 1st floor hard lids which are the lobby and electrical room. Also the General wants a consoltation for a 1st floor grid cover inspection borders only. Phone #: ###-#### Internet Inspection Request from: Don Lustig lobby hard lid, borders 1st floor only ok- will leave open if boxes and coordinate with electrician where working on heaters, no esc this project
|
ELE08-02010
| Permanent Service | 7/21/2008 | 7/21/2008 | 7/21/2008 1:30:34 PM | P | FAIL |
|
|
darrell Note: sp 69 Phone #: ###-#### called contractor, left correction notice, NEC 352.30(A) pvc shall be secured within 3' of panel,312.5 conductors entering enclosure shall have abrasion protection, 250.94 shall provide intersystem bonding termination at service and additional building, no esc for this project
|
ELE08-00642
| Electrical Rough-In | 7/21/2008 | 7/21/2008 | 7/21/2008 12:40:08 PM | P | PASS |
|
|
pat Phone #: ###-#### ok to cover garage only, no esc this project
|
ELE08-01511
| Final | 7/18/2008 | 7/21/2008 | 7/21/2008 10:23:45 AM | A | CANC |
|
|
Phone #: ###-#### Internet Inspection Request from: Lee VanSchoiack called contractor, he wants to reschedule, no esc this project
|
ELE08-02000
| Permanent Service | 7/18/2008 | 7/21/2008 | 7/21/2008 10:17:23 AM | A | FAIL |
|
|
glen Phone #: ###-#### Note: please call 1/2 hr prior to inspection to meet with met contractor, nec 250.94 shall provide intersystem bonding connector, and water pipe ground, will recall, no esc this project
|
ELE08-02000
| Final | 7/18/2008 | 7/21/2008 | 7/21/2008 10:16:17 AM | A | FAIL |
|
|
glen Phone #: ###-#### see p/s, no es this project
|
ELE08-02001
| Rough-In Permanent Service | 7/18/2008 | 7/21/2008 | 7/21/2008 9:31:01 AM | A | DONE |
|
|
Phone #: ###-#### Internet Inspection Request from: Bob Glenn inspection done 7-18-08
|
ELE08-00306
| Electrical Rough-In | 7/21/2008 | 7/21/2008 | 7/21/2008 9:24:36 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 7/21/2008 at 6:45:26 AM. Contact: ###-####., walls only ok to cover, no esc this project
|
ELE08-00307
| Electrical Rough-In | 7/21/2008 | 7/21/2008 | 7/21/2008 9:09:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 7/21/2008 at 6:44:01 AM. Contact: ###-####. called, walls only ok to cover, no esc this project
|
ELE08-01998
| Electrical Rough-In | 7/18/2008 | 7/21/2008 | 7/21/2008 8:39:44 AM | A | PART |
|
|
Phone #: ###-#### Internet Inspection Request from: HARVEY REYNA called, left message, left correction notice, BCC all underground shall be inspected before cover, NEC 250.94 intersystem bonding termination shall be provided at service and additional building, 300.5(D)(4) shall use schedule 80 pvc where emerging from grade
|
ELE08-01507
| Final | 7/20/2008 | 7/21/2008 | 7/21/2008 8:01:44 AM | A | PASS |
|
|
Hello i will stop by with the panel scheduals and general says he is finished Thanks Phone #: ###-#### Internet Inspection Request from: Don Lustig corrections made, ok to final, no esc this project, signed occupancy card
|
ELE08-02001
| Rough-In Permanent Service | 7/21/2008 | 7/21/2008 | 7/21/2008 8:01:43 AM | P | PASS |
|
|
called contractor, ric ok, p/s u/g n ok
|