Inspections for the day of: Tuesday, July 21, 2015.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorThomas Walsh
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00850 INSP-Final Inspection7/20/20157/21/20157/21/2015 4:19:38 PMPPASS
Continuation fo fire alarm testing, including trip test of dry pipe fire sprinkler system and reinspection of some devices (SFDs) that did operate properly at last inspection. Verified off site monitoring and correct address. System will remain in service from this point on.
NOTE: A question regarding any ADA - Hearing Impaired rooms, and the fire alarm contractor said that he was not aware of any. The GC said that there were three HI units. Therfore these units will have to be fitted with spreaker strobes in all rooms, including the bathrooms. This change may require a resubmittal to the fire alarm plan checker to verify system capability and battery capacity.
FIR14-00866 INSP-Final Inspection7/20/20157/21/20157/21/2015 4:14:27 PMPPASS
Trip test of the dry pipe valve, including the new accelerator - tested OK within 45 seconds.
Fire sprinklers for the entire project have been tested with fire alarm interface. Inspection with final walk through needs to be conducted prior to final sign-off, including obtaining ROCs. Systems are to remain in service from this point on.
FIR14-00815 INSP-Sprinkler Rough-in/Hydro7/20/20157/21/20157/21/2015 4:11:04 PMPCANC
Hydrotest cancelled for all systems. Not ready
FIR14-00792 INSP-Sprinkler Rough-in/Hydro7/21/20157/21/20157/21/2015 12:22:50 PMPPART
RTC inspection for Bldg H basement and first floor hard lid areas - see plans for areas inspected today.
OK to cover pipe in these areas.
FIR14-00365 INSP-Conference7/21/20157/21/20157/21/2015 11:18:26 AMPDONE
Meeting with elect. contractor (Tony) to discuss clearance around hose valve from emergency lighting unit.