Inspections for the day of: Thursday, July 21, 2016.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00365 INSP-Sprinkler Rough-in7/21/20167/21/20167/21/2016 3:22:02 PMPPASS
Rough to cover inspection for overhead fire sprinkler piping per this scope of work complete, overhead fire sprinkler piping per this scope of work approved for cover.
FIR16-00466 INSP-Final Inspection7/21/20167/21/20167/21/2016 3:20:32 PMPPASS
Final fire sprinkler inspection passed/complete.
FIR16-00266 INSP-Sprinkler Rough-in/Hydro7/19/20167/21/20167/21/2016 1:15:37 PMAPASS
Hydrostatic test complete for levels 1, 2, 3 and 4 overhead fire sprinkler piping. Overhead fire sprinkler piping that is not in attic space is approved for cover, overhead fire sprinkler piping located in attic spaces cannot be covered until tenting insulation inspection is complete, overhead fire sprinkler piping that gets covered before tenting inspection is completed will have any and all cover removed for tenting inspection.
FIR16-00266 INSP-Supply line flush7/20/20167/21/20167/21/2016 1:08:44 PMAPASS
Inspection request was for underground hydrostatic test and underground rough to cover, not a flush. Underground hydrostatic test passed/complete, underground supply approved for cover, flush will be completed at a later date.
FIR16-00450 INSP-Supply line flush7/20/20167/21/20167/21/2016 1:08:17 PMAPASS
Inspection request was for underground hydrostatic test and underground rough to cover, not a flush. Underground hydrostatic test passed/complete, underground supply approved for cover, flush will be completed at a later date.
FIR16-00322 INSP-Supply line flush7/20/20167/21/20167/21/2016 1:07:44 PMAPASS
Inspection request was for underground hydrostatic test and underground rough to cover, not a flush. Underground hydrostatic test passed/complete, underground supply approved for cover, flush will be completed at a later date.
FIR16-00275 INSP-Sprinkler Rough-in7/20/20167/21/20167/21/2016 10:38:00 AMPPASS
Rough to cover inspection for overhead fire sprinkler piping on level 7 complete, overhead fire sprinkler piping located on level 7 approved for cover.
FIR16-00275 INSP-Sprinkler Rough-in/Hydro7/20/20167/21/20167/21/2016 10:36:39 AMAPASS
Hydrostatic test complete for overhead fire sprinkler piping located on level 7.
FIR16-00323 INSP-Final Inspection7/20/20167/21/20167/21/2016 9:45:24 AMAPASS
Final fire sprinkler inspection passed/complete
BLD15-04136 FIRE-Final Inspection7/20/20167/21/20167/21/2016 9:25:01 AMAPASS
No fire sprinklers, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
FIR16-00243 INSP-Final Inspection7/20/20167/21/20167/21/2016 9:22:31 AMAPASS
Final fire alarm inspection passed/complete.
FIR16-00450 INSP-Supply line flush7/20/20167/21/20167/20/2016 11:50:17 AMACANC
Underground rough inspection. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
FIR16-00322 INSP-Supply line flush7/20/20167/21/20167/20/2016 11:50:14 AMACANC
Underground rough inspection. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello