FIR16-00365
| INSP-Sprinkler Rough-in | 7/21/2016 | 7/21/2016 | 7/21/2016 3:22:02 PM | P | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping per this scope of work complete, overhead fire sprinkler piping per this scope of work approved for cover.
|
FIR16-00466
| INSP-Final Inspection | 7/21/2016 | 7/21/2016 | 7/21/2016 3:20:32 PM | P | PASS |
|
|
Final fire sprinkler inspection passed/complete.
|
FIR16-00266
| INSP-Sprinkler Rough-in/Hydro | 7/19/2016 | 7/21/2016 | 7/21/2016 1:15:37 PM | A | PASS |
|
|
Hydrostatic test complete for levels 1, 2, 3 and 4 overhead fire sprinkler piping. Overhead fire sprinkler piping that is not in attic space is approved for cover, overhead fire sprinkler piping located in attic spaces cannot be covered until tenting insulation inspection is complete, overhead fire sprinkler piping that gets covered before tenting inspection is completed will have any and all cover removed for tenting inspection.
|
FIR16-00266
| INSP-Supply line flush | 7/20/2016 | 7/21/2016 | 7/21/2016 1:08:44 PM | A | PASS |
|
|
Inspection request was for underground hydrostatic test and underground rough to cover, not a flush. Underground hydrostatic test passed/complete, underground supply approved for cover, flush will be completed at a later date.
|
FIR16-00450
| INSP-Supply line flush | 7/20/2016 | 7/21/2016 | 7/21/2016 1:08:17 PM | A | PASS |
|
|
Inspection request was for underground hydrostatic test and underground rough to cover, not a flush. Underground hydrostatic test passed/complete, underground supply approved for cover, flush will be completed at a later date.
|
FIR16-00322
| INSP-Supply line flush | 7/20/2016 | 7/21/2016 | 7/21/2016 1:07:44 PM | A | PASS |
|
|
Inspection request was for underground hydrostatic test and underground rough to cover, not a flush. Underground hydrostatic test passed/complete, underground supply approved for cover, flush will be completed at a later date.
|
FIR16-00275
| INSP-Sprinkler Rough-in | 7/20/2016 | 7/21/2016 | 7/21/2016 10:38:00 AM | P | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 7 complete, overhead fire sprinkler piping located on level 7 approved for cover.
|
FIR16-00275
| INSP-Sprinkler Rough-in/Hydro | 7/20/2016 | 7/21/2016 | 7/21/2016 10:36:39 AM | A | PASS |
|
|
Hydrostatic test complete for overhead fire sprinkler piping located on level 7.
|
FIR16-00323
| INSP-Final Inspection | 7/20/2016 | 7/21/2016 | 7/21/2016 9:45:24 AM | A | PASS |
|
|
Final fire sprinkler inspection passed/complete
|
BLD15-04136
| FIRE-Final Inspection | 7/20/2016 | 7/21/2016 | 7/21/2016 9:25:01 AM | A | PASS |
|
|
No fire sprinklers, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
FIR16-00243
| INSP-Final Inspection | 7/20/2016 | 7/21/2016 | 7/21/2016 9:22:31 AM | A | PASS |
|
|
Final fire alarm inspection passed/complete.
|
FIR16-00450
| INSP-Supply line flush | 7/20/2016 | 7/21/2016 | 7/20/2016 11:50:17 AM | A | CANC |
|
|
Underground rough inspection. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
FIR16-00322
| INSP-Supply line flush | 7/20/2016 | 7/21/2016 | 7/20/2016 11:50:14 AM | A | CANC |
|
|
Underground rough inspection. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|