Inspections for the day of: Tuesday, July 21, 2020.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-04134 BLD-Final7/20/20207/21/20207/21/2020 4:07:56 PMPNR
The bank''s lobby is closed, you will need to knock on the door to get the occupants to let you in. Phone #: ###-#### Inspection requested via web by Mark Fledderjohann. Needs fire final first.
BLD18-03143 BLD-Framing/Rough-in7/21/20207/21/20207/21/2020 4:07:00 PMPCANC
Firestop assemblies, SE Shaft. Other areas outlined between Forte and ESI. Call adam when heading to site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD20-01968 BLD-Final7/20/20207/21/20207/21/2020 2:35:29 PMPPASS
call 15 mins for access- Dan *screened* Phone #: ###-####. Ok for perm occ.
BLD20-01478 BLD-Foundation7/20/20207/21/20207/21/2020 2:35:04 PMPPART
Patrick *screened* Phone #: ###-####. Ok for mono placement. Needs to dig out bottom of footing in north east corner. Ok to place concrete.
BLD20-02435 BLD-Final7/21/20207/21/20207/21/2020 2:32:42 PMPDONE
Inspection requested via web by Richard Murray
BLD20-02435 DOC - Permit Finaled7/21/20207/21/20207/21/2020 2:32:32 PMPPASS
All work appeared to be done inn accordance with local codes and ordinances.
BLD18-03143 BLD-Ceiling Grid Inspection7/21/20207/21/20207/21/2020 11:10:13 AMAPASS
First floor fat grid framing, and back of house ceiling grid cover inspection Phone #: ###-#### Inspection requested via web by Mike Beeson.. 1st floor hardlid in lobby and eatry ok. back of house not ready.
BLD20-01176 BLD-Framing/Rough-in7/20/20207/21/20207/21/2020 10:45:16 AMAPASS
Phone #: 2084014806 >> Inspection requested via mobile web by Denny Robertson. Hardlids ok.
BLD19-02339 BLD-Wall cover7/20/20207/21/20207/21/2020 10:22:27 AMAPASS
Andy *screened* Phone #: ###-####. Elevator shaft walls for cars 3 and 4 on 10th. floor. Fire proofing patch back on west coloumn north notch. Stair 2 shaft walls floor 6 to 10. main mech shaft floor 3.
BLD19-00645 BLD-Blower Door Test Results7/21/20207/21/20207/21/2020 9:17:34 AMADONE
4.9
ESC19-00236 Site Final7/21/20207/21/20207/21/2020 9:17:13 AMADONE
ESC19-00236 DOC - Permit Finaled7/21/20207/21/20207/21/2020 9:17:04 AMPPASS
BLD19-00645 BLD-Final7/20/20207/21/20207/21/2020 9:16:51 AMAPASS
SCREENED // call for access ...... Tyler Phone #: ###-####
BLD19-00645 DOC - Permit Finaled7/21/20207/21/20207/21/2020 9:16:40 AMPPASS
BLD20-00026 BLD-Framing/Rough-in7/20/20207/21/20207/21/2020 8:53:02 AMAPASS
SCREENED // Todd Phone #: ###-####. Ok to cover exterior sheathing and roof.
BLD20-00700 BLD-Framing/Rough-in7/20/20207/21/20207/21/2020 8:31:22 AMAPASS
Rod *screened* Phone #: ###-####. soffits, hardlids and furred walls for remainder of interior framing ok.