BLD02-03033
| FIRE-Final Inspection | 7/21/2004 | 7/22/2004 | 7/22/2004 12:00:00 AM | A | FAIL |
|
|
Provide lever hardware per approved plans on all doors. Remove thumbturn from main entry/exit. Provide sticker as discussed on the main entry/exit. Provide verification the HVAC units are under 2000cfm. 7/22/2004 10:02:14 AM
|
BLD04-01019
| FIRE-Final Inspection | 7/21/2004 | 7/22/2004 | 7/22/2004 12:00:00 AM | A | PASS |
|
|
Life safety finaled 7/22/2004 8:33:19 AM
|
FIR04-00378
| INSP-Final Inspection | 7/22/2004 | 7/22/2004 | 7/22/2004 12:00:00 AM | A | PASS |
|
|
Fire sprinklers finaled
|
FIR04-00370
| INSP-Sprinkler Rough-in/Hydro | 7/22/2004 | 7/22/2004 | 7/22/2004 12:00:00 AM | P | PASS |
|
|
Sprinkler rough-in OK. Need new hydraulic sticker, spare heads and tape off of sprinkler uprights to final. 7/22/2004 3:46:36 PM
|
FIR03-00779
| INSP-Sprinkler Rough-in/Hydro | 7/22/2004 | 7/22/2004 | 7/22/2004 12:00:00 AM | P | PART |
|
|
Forward flush of the backflow preventer and the additional head in the closet are ok. Still need alarm connections and hanger from previous correction notice to be done. 7/22/2004 1:58:54 PM
|
FIR04-00370
| INSP-Sprinkler Rough-in/Hydro | 7/22/2004 | 7/22/2004 | 7/22/2004 12:00:00 AM | P | PART |
|
|
Hydro test OK. 7/22/2004 11:18:46 AM
|
FIR04-00407
| INSP-Conference | 7/22/2004 | 7/22/2004 | 7/22/2004 12:00:00 AM | P | DONE |
|
|
Met with tim, superintendant, and a representative from the mechanical and fire alarm contractors. We discussed the removal of a duct smoke detector that was not needed in the Training room. The hvac unit is 1800cfm and serves only that room. I agreed with the removal 7/22/2004 3:48:31 PM
|