Inspections for the day of: Wednesday, July 22, 2009.
Number of inspections: 23
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Strole
TitlePLM/MEC-INSPECTOR
Phone #794-7913
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM08-01619 Final7/21/20097/22/20097/23/2009 2:53:09 PMPNR
FINAL TO CLOSE PERMIT Internet Inspection Request from: Allison Briggs
PLM09-01090 Roof Drains7/21/20097/22/20097/23/2009 7:36:38 AMPPART
test on south side pass, need to complete west side.
PLM09-00947 Final7/22/20097/22/20097/22/2009 3:47:33 PMPPASS
Jeff Phone #: ###-####
ESC07-00319 Aging Inspection7/22/20097/22/20097/22/2009 3:23:31 PM PASS
ESC07-00319 Site Final7/22/20097/22/20097/22/2009 3:23:20 PMPPASS
PLM09-01130 Water and/or Sewer7/22/20097/22/20097/22/2009 3:22:16 PMPCANC
PLM09-01165 Groundwork7/22/20097/22/20097/22/2009 3:04:36 PMPPART
###-#### Jeff Jim - after 2 pm if possible-dwv center and west side pass. need east side and grease line to complete yet.
PLM09-01162 Water and/or Sewer7/21/20097/22/20097/22/2009 1:57:44 PMPPASS
kelly Phone #: ###-####
PLM09-01162 DOC - Permit Finaled7/22/20097/22/20097/22/2009 1:57:31 PMPPASS
kelly Phone #: ###-####
ESC09-00416 Random Inspection7/22/20097/22/20097/22/2009 1:46:01 PMPPART
sewer contractor will clean up tracking after backfill & by days end.
PLM09-01169 DOC - Permit Finaled7/22/20097/22/20097/22/2009 1:44:40 PMPPASS
Brett Phone #: ###-####
PLM09-01140 Plumbing Rough-in7/17/20097/22/20097/22/2009 11:04:52 AMANH
Dana is contact Phone #: ###-#### Internet Inspection Request from: Angie Redfern-no access
PLM09-01054 Water and/or Sewer7/21/20097/22/20097/22/2009 10:41:41 AMANR
Scheduled by a contractor via Hello! on 7/21/2009 at 8:34:57 PM. Contact: ###-####.
PLM09-01152 Water and/or Sewer7/22/20097/22/20097/22/2009 10:02:28 AMAFAIL
need to support pex in crawl every 32". #1 ballvalve on rpba is where the #2 ballvalve should be. need thermal expantion tank down stream of dbca. rpba & dbca need tested & certified. ok to cover waterline.
PLM09-01020 Plumbing Rough-in7/21/20097/22/20097/22/2009 9:33:58 AMAPASS
Rocky Phone #: ###-####
ESC09-00310 Random Inspection7/22/20097/22/20097/22/2009 9:06:32 AMAPART
spoke with rp about sweaping dirt & debris off all hard surfaces at the end of each day, also stock pile is going to be moved to lot north of site for top soil.
ESC09-00309 Random Inspection7/22/20097/22/20097/22/2009 9:06:13 AMAPART
spoke with rp about sweaping dirt & debris off all hard surfaces at the end of each day, also stock pile is going to be moved to lot north of site for top soil.
PLM09-01131 Water and/or Sewer7/21/20097/22/20097/22/2009 8:57:31 AMAPASS
call mike kelly to schedule rough ###-#### Phone #: ###-#### Internet Inspection Request from: Allison Briggs
PLM09-01131 DOC - Permit Finaled7/22/20097/22/20097/22/2009 8:57:20 AMPPASS
call mike kelly to schedule rough ###-#### Phone #: ###-#### Internet Inspection Request from: Allison Briggs
PLM09-01130 Water and/or Sewer7/21/20097/22/20097/22/2009 8:57:00 AMAFAIL
call mike kelly to schedule rough ###-#### habitat house Phone #: ###-#### Internet Inspection Request from: Allison Briggs-waterline pass, need to use approved material for sewer inside building.
ESC07-00221 Aging Inspection7/22/20097/22/20097/22/2009 8:15:31 AM PASS
ESC07-00221 Site Final7/22/20097/22/20097/22/2009 8:15:19 AMPPASS
PLM09-01094 Water and/or Sewer7/21/20097/22/20097/22/2009 7:17:51 AMACANC