Inspections for the day of: Tuesday, July 22, 2014.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00460 INSP-Sprinkler Rough-in7/22/20147/22/20147/23/2014 2:49:31 PMPPART
Okay to cover UG fire supply line
BLD14-01232 FIRE-Final Inspection7/22/20147/22/20147/22/2014 3:01:12 PMPPASS
Life safety passed provided door hardware, including signage, per plan review annotations at the main entry/exit is revised prior to structural final inspection.
FIR14-00269 INSP-Sprinkler Rough-in7/22/20147/22/20147/22/2014 2:58:02 PMPPART
Inspection for cover at grid ceilings completed to date- Items noted include; insufficient coverage the janitors and IT rooms due to OTS ceiling configuration, need to add upright coverage at a concealed space overbuild above classroom 119. Commons classroom, corridor grid, and main tie-in above the 5th grade classroom are not yet finished. Verified added uprights along the north and south main corridor rated walls. Discussed hydrostatic testing per review notes and NFPA guidelines. Need record drawings for field modifications. Remainder of classrooms approved for ceiling cover as noted on plans.
BLD13-01344 FIRE-Final Inspection7/21/20147/22/20147/22/2014 1:36:24 PMPFAIL
Correction items include; post building address numbers, install exit signs per plan sheet AS 101, provide fire extinguisher, door hardware at the restrooms needs to meet egress requirements per IBC.
FIR14-00368 INSP-Final Inspection7/21/20147/22/20147/22/2014 11:59:06 AMAPART
Pharmacy area remodel and coffee shop kiosk both passed final walkthrough. Final pending one demo head per plans. Noted existing fire sprinkler system appears overdue annual certification and inspection.
BLD13-03418 FIRE-Final Inspection7/21/20147/22/20147/22/2014 10:07:49 AMAPART
Regarding completion of work at the basement level.
FIR14-00327 INSP-Sprinkler Rough-in7/21/20147/22/20147/22/2014 10:06:43 AMAPART
Okay to cover overhead work at the corridor grid ceiling areas.