Inspections for the day of: Friday, July 22, 2016.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00273 FIR-Aging Inspection7/22/20167/22/20167/22/2016 2:50:52 PM CANC
FIR16-00363 INSP-Alarm Testing7/22/20167/22/20167/22/2016 1:58:12 PMPCANC
Inspection request cancelled, no point of contact information was given for this project, contacted Protex Office, phone number ###-####, phone call went to voicemail, left a message stating that if a point of contact is not provided then inspection request will need to be rescheduled.
BLD15-01107 FIRE-Final Inspection7/21/20167/22/20167/22/2016 1:54:27 PMPCANC
Inspection request cancelled per conversation with point of contact, Ed Phone #: ###-####. Fire alarm contractor has to make changes to the audio visual devices located in the bathrooms with the showers, when modifications are completed a final fire alarm inspection will be called in to coincide with the final life fire safety inspection.
FIR15-00861 INSP-Sprinkler Rough-in/Hydro7/22/20167/22/20167/22/2016 1:31:59 PMPPASS
Rough to cover inspection complete for level 7, hydrostatic test complete for overhead fire sprinkler piping on level 7, tamper switch and flow switch satisfactorily tested for level 7.
FIR15-00831 INSP-Sprinkler Rough-in/Hydro7/21/20167/22/20167/22/2016 1:28:41 PMAPASS
Rough to cover inspection complete for level 6, hydrostatic test complete for overhead fire sprinkler piping on level 6, tamper switch and flow switch satisfactorily tested for level 6.
FIR16-00010 INSP-Sprinkler Rough-in/Hydro7/21/20167/22/20167/22/2016 1:27:36 PMAPASS
Rough to cover inspection complete for level 8, hydrostatic test complete for overhead fire sprinkler piping on level 8, tamper switch and flow switch satisfactorily tested for level 8.
FIR16-00075 INSP-Sprinkler Rough-in/Hydro7/21/20167/22/20167/22/2016 1:22:52 PMAPASS
Rough to cover inspection complete for level 9, hydrostatic test complete for overhead fire sprinkler piping on level 9, tamper switch and flow switch satisfactorily tested for level 9.
FIR16-00155 INSP-Sprinkler Rough-in7/21/20167/22/20167/22/2016 1:16:42 PMAPASS
Rough to cover inspection for hardlids located in the restrooms, 4th floor northside complete, hardlids approved for cover.
FIR16-00204 INSP-Sprinkler Rough-in7/21/20167/22/20167/22/2016 11:05:09 AMAPASS
24 hour air test for preaction system complete, 200 psi hydrostatic test for preaction system complete.
FIR15-00635 INSP-Final Inspection7/20/20167/22/20167/22/2016 10:00:26 AMAPASS
Final fire sprinkler inspection passed/complete
FIR15-00561 INSP-Sprinkler Rough-in7/21/20167/22/20167/22/2016 9:07:59 AMAPASS
Rough to cover inspection for overhead fire sprinkler piping located on level 4 complete, overhead fire sprinkler piping located on level 4 approved for cover. Rough to cover inspection complete for overhead fire sprinkler piping located above the hardlids on level 1, overhead fire sprinkler piping located above the hardlids on level 1 approved for cover.
BLD16-01260 FIRE-Final Inspection7/21/20167/22/20167/22/2016 8:35:44 AMAPASS
No fire sprinkler modifications, fire alarm inspection complete (FIR permit was not attached in project related cases FIR16-00381), fire extinguishers are in common area's with current inspections tags. Final life fire safety inspection passed/complete.
FIR15-00795 INSP-Final Inspection7/20/20167/22/20167/21/2016 5:23:15 PMACANC
Please call Jake when you are headed out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello