ESC14-00928
| General Inspection | 7/20/2016 | 7/22/2016 | 7/22/2016 4:03:00 PM | A | PASS |
|
|
follow up BMP violation for sweeping/housekeeping
DI bag was changed out as requested. Sweep up in progress. Will check conditions early next week. Initial request has been addressed by RP. Approved.
|
ESC15-01612
| Aging Inspection | 7/22/2016 | 7/22/2016 | 7/22/2016 3:21:08 PM | | CANC |
|
|
rescheduled for site final next week. Landscaping and final clean up is in progress.
|
ESC16-00603
| Site Preparation | 7/22/2016 | 7/22/2016 | 7/22/2016 3:18:11 PM | P | PASS |
|
|
Central Paving on site setting up staging area. Silt fence along bottom of site and rock construction entrance. Plan is to leave a channel through site to convey any flash flooding that could potentially occur. Currently the creek is dry. SWPPP box and ESC permit on site. Approved. eNOI is active, tracking # IDR12AM85
|
ESC15-01564
| Aging Inspection | 7/22/2016 | 7/22/2016 | 7/22/2016 2:44:20 PM | | PASS |
|
|
Final landscaping and site clean up in progress. Once complete, will have Brighton Homes pull all temporary sediment filter bags from Mill District Square storm drains.
|
ESC16-00659
| General Inspection | 7/22/2016 | 7/22/2016 | 7/22/2016 2:31:59 PM | P | PASS |
|
|
WIP on framing. No sediment or other materials leaving site. Trash and materials contained. Clean site. Permit sign posted.
|
ESC15-01389
| General Inspection | 7/21/2016 | 7/22/2016 | 7/22/2016 2:25:34 PM | P | PASS |
|
|
Home now complete and occupied. Adjacent lot was cleaned up as requested. Yard landscaped and stabilzed. ESC conditions satisfied.
|
ESC15-01389
| DOC - Permit Finaled | 7/22/2016 | 7/22/2016 | 7/22/2016 2:24:08 PM | P | PASS |
|
|
|
ESC16-00868
| Site Preparation | 7/22/2016 | 7/22/2016 | 7/22/2016 10:23:08 AM | A | PASS |
|
|
BMPs installed. Permit sign posted. Approved for excavation. 6 total cottages at Bryn Mawr Cove
|
ESC16-00888
| Site Preparation | 7/21/2016 | 7/22/2016 | 7/22/2016 10:03:38 AM | A | PASS |
|
|
Bill Phone #: ###-####
Bill Phone #: ###-####
Site is prepared for excavation. Access drive and permeable pavers for parking were installed previously. MS4 inlet on Targee has sediment bag installed. Perimeter silt fence and clearing limit is established. Permit signs posted. Reminder to have trash containment and concrete washout during foundation work.
|
ESC16-00886
| Site Preparation | 7/21/2016 | 7/22/2016 | 7/22/2016 10:03:25 AM | A | PASS |
|
|
Bill Phone #: ###-####
Bill Phone #: ###-####
Site is prepared for excavation. Access drive and permeable pavers for parking were installed previously. MS4 inlet on Targee has sediment bag installed. Perimeter silt fence and clearing limit is established. Permit signs posted. Reminder to have trash containment and concrete washout during foundation work.
|
ESC16-00885
| Site Preparation | 7/21/2016 | 7/22/2016 | 7/22/2016 10:03:14 AM | A | PASS |
|
|
Bill Phone #: ###-####
Bill Phone #: ###-####
Site is prepared for excavation. Access drive and permeable pavers for parking were installed previously. MS4 inlet on Targee has sediment bag installed. Perimeter silt fence and clearing limit is established. Permit signs posted. Reminder to have trash containment and concrete washout during foundation work.
|
ESC16-00884
| Site Preparation | 7/21/2016 | 7/22/2016 | 7/22/2016 10:02:55 AM | A | PASS |
|
|
Bill Phone #: ###-####
Bill Phone #: ###-####
Site is prepared for excavation. Access drive and permeable pavers for parking were installed previously. MS4 inlet on Targee has sediment bag installed. Perimeter silt fence and clearing limit is established. Permit signs posted. Reminder to have trash containment and concrete washout during foundation work.
|
ESC16-00883
| Site Preparation | 7/21/2016 | 7/22/2016 | 7/22/2016 10:02:40 AM | A | PASS |
|
|
Bill Phone #: ###-####
Site is prepared for excavation. Access drive and permeable pavers for parking were installed previously. MS4 inlet on Targee has sediment bag installed. Perimeter silt fence and clearing limit is established. Permit signs posted. Reminder to have trash containment and concrete washout during foundation work.
|
ESC15-00667
| General Inspection | 7/22/2016 | 7/22/2016 | 7/22/2016 9:00:28 AM | | PEND |
|
|
Silt fence installed along drainage ditches need to be removed in order to final permit. No other issues, road shoulders and disturbed areas have been stabilzed.
|