BLD19-02519
| BLD-Final | 7/22/2019 | 7/22/2019 | 7/23/2019 11:07:01 AM | P | NR |
|
|
Please call Troy Mechsner Phone – (208)-###-#### to gain access to site for final inspection. Phone #: ###-#### Inspection requested via web by Dale Hope work in progress.
|
BLD06-02322
| BLD-Energy code compliance | 7/22/2019 | 7/22/2019 | 7/22/2019 4:18:21 PM | P | PASS |
|
|
Area B 3rd floor- Lee Phone #: ###-####
|
BLD06-02322
| BLD-Framing/Rough-in | 7/22/2019 | 7/22/2019 | 7/22/2019 4:18:04 PM | P | PASS |
|
|
Area B framing on stairs - Lee Phone #: ###-####
|
BLD19-02301
| BLD-Foundation | 7/19/2019 | 7/22/2019 | 7/22/2019 4:17:49 PM | P | PASS |
|
|
Chris - foundation wall Phone #: ###-####
|
BLD19-00769
| BLD-Framing/Rough-in | 7/22/2019 | 7/22/2019 | 7/22/2019 2:36:00 PM | P | PASS |
|
|
Ed Phone #: ###-#### c/n made ok
|
BLD19-00769
| BLD-Energy code compliance | 7/22/2019 | 7/22/2019 | 7/22/2019 2:35:40 PM | P | PASS |
|
|
Ed Phone #: ###-####
|
BLD18-03695
| BLD-Foundation | 7/22/2019 | 7/22/2019 | 7/22/2019 1:46:44 PM | P | PASS |
|
|
RICK- rebar inspection Phone #: ###-####
|
BLD19-00150
| BLD-Final | 7/19/2019 | 7/22/2019 | 7/22/2019 11:39:33 AM | A | PASS |
|
|
Corey Phone #: ###-####
|
BLD19-00150
| DOC - Permit Finaled | 7/22/2019 | 7/22/2019 | 7/22/2019 11:39:19 AM | P | PASS |
|
|
|
MIS19-00208
| DOC - Permit Finaled | 7/22/2019 | 7/22/2019 | 7/22/2019 11:07:39 AM | P | PASS |
|
|
|
MIS19-00209
| Set Bond Amount | 7/19/2019 | 7/22/2019 | 7/22/2019 10:47:15 AM | A | PASS |
|
|
Neil Phone #: ###-#### bond $10,000.00
|
BLD19-01950
| BLD-Other | 7/21/2019 | 7/22/2019 | 7/22/2019 10:37:43 AM | A | PASS |
|
|
Framing Inspection please! :) Phone #: ###-#### Inspection requested via web by Shane Leslie
|
BLD19-01075
| BLD-Wall Bracing | 7/21/2019 | 7/22/2019 | 7/22/2019 10:21:48 AM | A | PASS |
|
|
Please call above number when headed to job site. Plans are right inside the front door to the left as you enter. Phone #: ###-#### Inspection requested via web by Jeff Fawson
|
BLD18-03266
| BLD-Aging Inspection | 7/22/2019 | 7/22/2019 | 7/22/2019 9:56:49 AM | | PASS |
|
|
|
BLD19-01530
| BLD-Framing/Rough-in | 7/19/2019 | 7/22/2019 | 7/22/2019 9:55:43 AM | A | CANC |
|
|
I will be there in the A.M. to walk through things with you. The Heating is complete, just waiting to get troy to approve manual J that is current. He said he will review and approve monday morning. Please come so I can re-inspect in PM if necessary. Thanks Phone #: ###-#### Inspection requested via web by Nathan Taylor
|
BLD18-03233
| BLD-Final | 7/19/2019 | 7/22/2019 | 7/22/2019 9:55:42 AM | A | PASS |
|
|
Mike Phone #: ###-####
|