Inspections for the day of: Monday, July 22, 2019.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTom Saunders
TitleELE-INSPECTOR
Phone #208-794-1923
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-02462 Final7/22/20197/22/20197/22/2019 2:49:57 PMPPASS
Phone #: ###-#### Inspection requested via web by Jay Symonds...ok to final
ELE19-01529 Conference7/19/20197/22/20197/22/2019 2:40:27 PMPPASS
Looking for a status check on the work done so far. I am having minor finger surgery at 1:00 which should take about 1:00. Hoping to schedule conference after 3:00. Phone #: ###-#### Inspection requested via web by Ron MacCulloch...discussed connection to sub panel and make-up of switches and outlets...future rough-in inspection and final inspection requirements
ELE19-01529 Electrical Rough-In7/22/20197/22/20197/22/2019 2:38:11 PMPPASS
Phone #: ###-#### Inspection requested via web by Ron MacCulloch...
approval for column cover and ceiling cover only of patio addition
ELE19-02065 Final7/22/20197/22/20197/22/2019 1:51:35 PMPFAIL
Chad Vanorden is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce....
1) all receptacles within 6ft of sink shall have GFCI protection...unable to verify 240V outlet in breakroom
2) access for HVAC disconnect above grid shall have access...unable to verify
ELE19-01820 Electrical Rough-In7/22/20197/22/20197/22/2019 1:03:21 PMPPASS
Jeff- please call for access Phone #: ###-####...
rough-in of new all-in one with overhead feed..ok
ELE19-01820 Permanent Service7/22/20197/22/20197/22/2019 1:01:58 PMPPASS
Jeff- please call for access Phone #: ###-####...
p/s o/h new ok
ELE19-02558 Final7/18/20197/22/20197/22/2019 10:14:20 AMACANC
Brittany Phone #: ###-####...
Boise city ordinance requires a rough inspection of solar install before a final can be given
job is complete...panels need removed and brought to ground level for inspection of listing and labelling...licensed electrician required to be on sight for inspection...spoke with Virginia solar rep and made aware of requirements 7/22/19 at 10AM
ELE19-02162 Final7/22/20197/22/20197/22/2019 9:59:14 AMAPASS
job complete...labelling, disconnect, and OCPD ok
ELE19-02162 Electrical Rough-In7/19/20197/22/20197/22/2019 9:57:20 AMAPASS
Taylor Barton is best contact Phone #: ###-#### Inspection requested via web by BRS Permitting....UL listed equipment and grounding verified
ELE19-02689 Electrical Rough-In7/21/20197/22/20197/22/2019 9:30:57 AMAPASS
Underground wire depth check. Please call me and give me 10 minutes to leave work. I''d like to chat about getting it to house. Phone #: ###-#### Inspection requested via web by Brad Downs...
trench with UF wire to 2 outlet locations and garage wall...ok to cover
ELE19-02691 Final7/19/20197/22/20197/22/2019 9:11:39 AMAPASS
Mike Phone #: ###-####...complete ok to final
ELE19-00631 Electrical Rough-In7/19/20197/22/20197/22/2019 9:08:48 AMAPASS
Phone #: ###-#### Inspection requested via web by Kerri Hamilton...
exterior soffit cans..2 locations...ok to cover
ELE19-02062 Final7/19/20197/22/20197/22/2019 8:11:28 AMAFAIL
power to sign. Phone #: ###-#### Inspection requested via web by Kendra Lanham..
1) rough in inspection other then underground shall be schedule before final...material used and wiring methods need verified
2) access to panel to verify panel labelling and circuit rating ok