Inspections for the day of: Monday, July 23, 2018.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTony Young
TitleBLD-COM/RES INSPECTOR
Phone #794-9462
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-01859 BLD-Footing7/23/20187/23/20187/24/2018 10:51:54 AMPNR
Phone #: 2085736921 >> Inspection requested via mobile web by Jimmy,, still needs soils approval
BLD18-01518 BLD-Footing7/20/20187/23/20187/23/2018 4:23:05 PMPNR
pergola - Ken Phone #: ###-####
BLD18-01316 BLD-Final7/20/20187/23/20187/23/2018 3:47:04 PMPPASS
Larry Phone #: ###-####
BLD18-01316 DOC - Permit Finaled7/23/20187/23/20187/23/2018 3:46:58 PMPPASS
BLD16-03251 BLD-Final7/23/20187/23/20187/23/2018 3:33:54 PMPPASS
Rosie-please go as late as possible as the ele is early pm Phone #: ###-####
BLD16-03251 DOC - Permit Finaled7/23/20187/23/20187/23/2018 3:33:26 PMPPASS
c of c/o issued
BLD17-01297 BLD-Footing7/23/20187/23/20187/23/2018 3:01:18 PMPPART
Rebar - Please call ahead // TJ Phone #: ###-####,, footings, work in progress,, ok
BLD18-00653 BLD-Final7/23/20187/23/20187/23/2018 3:00:42 PMPNR
Home will be open Phone #: ###-#### Inspection requested via web by bryan murdoch,, needs trades,, needs address also
BLD17-02032 BLD-Conference7/20/20187/23/20187/23/2018 2:19:21 PMANR
Please call to let him know if he passed // Rob Phone #: ###-####/// take plan review out to site
BLD18-00843 BLD-Framing/Rough-in7/23/20187/23/20187/23/2018 2:18:25 PMPPART
Phone #: ###-#### Inspection requested via web by Joseph knight,, work in progress on exterior shear,, not readt for a frame inspection
MIS18-00268 BLD-Conference7/20/20187/23/20187/23/2018 2:12:30 PMAFAIL
there is a shed being built in the side/rear setback,, call into Sue C. to find out what the setbacks are.. left a SWO due to possible set backs, zoning approval
BLD18-02302 BLD-Footing7/20/20187/23/20187/23/2018 1:46:23 PMPPART
Derik Phone #: ###-####,, garage footing ok
BLD18-02455 BLD-Final7/21/20187/23/20187/23/2018 1:12:43 PMADONE
need final Phone #: ###-#### Inspection requested via web by Chris Howell
BLD18-02455 DOC - Permit Finaled7/23/20187/23/20187/23/2018 1:12:36 PMPPASS
BLD18-01895 BLD-Framing/Rough-in7/20/20187/23/20187/23/2018 1:12:13 PMAPASS
Dan Phone #: ###-####,, ok after fixing a couple things,, adding hardware
BLD18-00944 BLD-Foundation7/20/20187/23/20187/23/2018 1:09:58 PMAPART
Curt Phone #: ###-####,, work in progress,, special inspection will happen
BLD18-00881 BLD-Energy code compliance7/20/20187/23/20187/23/2018 11:50:49 AMAPART
Ron Phone #: ###-####,, under wood floor top of existing slab rigid foam ok
BLD17-01297 BLD-Footing7/20/20187/23/20187/23/2018 10:35:08 AMAPEND
Rebar - Please call ahead // TJ Phone #: ###-####,, needs soils approval 1st
BLD18-01859 BLD-Footing7/20/20187/23/20187/23/2018 10:34:10 AMANR
Phone #: 2085736921 >> Inspection requested via mobile web by Jimmy,, needs soils approval
BLD18-02528 BLD-Footing7/20/20187/23/20187/23/2018 10:10:27 AMPCANC
James Phone #: ###-#### Inspection cancelled from web by: Keeley Wilson