Inspections for the day of: Thursday, July 23, 2020.
Number of inspections: 1
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorChad Schwendiman
TitleMEC-INSPECTOR
Phone #780-9549
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC20-02876 Conference7/23/20207/23/20207/23/2020 9:53:30 AMADONE
Meet onsite to discuss TCO requirements. Currently the teachers are planning to be in classroom Aug. 7th and school starting Aug. 17th. There is a delay in the shipping of the roof top equipment for this project. The indoor units and work will be completed prior to the teachers being in the classroom however the roof top equipment will not be so the units will not be functional. I told them I would be okay with a TCO for the teachers only to be in the classrooms without the HVAC system being functional, but that the system will have to be fully functional prior to kids being allowed in the classroom.