Inspections for the day of: Thursday, July 23, 2020.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR20-00490 INSP-Sprinkler Rough-in7/22/20207/23/20207/23/2020 4:06:45 PMPPASS
Rough to cover inspection for scope of work complete, approved for cover.

please give Mike a heads up on your way Phone #: ###-#### Inspection requested via web by jeremiah robison
FIR19-00702 INSP-Final Inspection7/22/20207/23/20207/23/2020 2:26:19 PMPPASS
Previously noted items on the 22JULY2020 inspection have been corrected, final fire sprinkler inspection is complete.

Coordinate a time with James. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
FIR19-00681 INSP-Final Inspection7/22/20207/23/20207/23/2020 2:12:34 PMPFAIL
Provide small documents as discussed. Fire sprinkler monitoring is complete. Room notification did not function on general alarm.

Fire alarm inspection. Phone #: ###-#### Inspection requested via web by Ashley Chapman
FIR19-00702 INSP-Sprinkler Rough-in/Hydro7/22/20207/23/20207/23/2020 11:02:29 AMADONE
Hydrostatic test witnessed, no pressure loss observed at riser provided gauges.

Hydro, all floors. Call James before heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
FIR20-00428 INSP-Final Inspection7/23/20207/23/20207/23/2020 9:24:38 AMAPASS
Final fire sprinkler inspection for area of work is complete.
FIR20-00428 INSP-Sprinkler Rough-in/Hydro7/23/20207/23/20207/23/2020 9:24:12 AMACANC
FIR20-00403 INSP-Final Inspection7/20/20207/23/20207/23/2020 9:10:55 AMAPASS
Final fire sprinkler inspection for area of work is complete.

Phone #: ###-#### Inspection requested via web by Brian Carlisle
FIR20-00401 INSP-Final Inspection7/20/20207/23/20207/23/2020 9:10:34 AMAPASS
Final fire sprinkler inspection for area of work is complete.

Phone #: ###-#### Inspection requested via web by Brian Carlisle
FIR20-00402 INSP-Final Inspection7/20/20207/23/20207/23/2020 9:10:15 AMAPASS
Final fire sprinkler inspection for area of work is complete.

Phone #: ###-#### Inspection requested via web by Brian Carlisle
FIR19-00522 INSP-Final Inspection7/20/20207/23/20207/23/2020 9:09:35 AMACANC
Inspection request cancelled per conversation with point of contact, demo work done by others in suite 186 without permits, due too demo work troubles are on the panel. Instructed GC with RRC for space 186 the proper requirements prior to demo work.

Please Give Mike a call 1 hour prior to arrival. Phone #: ###-#### Inspection requested via web by James Williams
FIR20-00401 INSP-Sprinkler Rough-in7/20/20207/23/20207/23/2020 9:06:43 AMAPASS
Rough to cover inspection for area of work complete, approved for cover.

Phone #: ###-#### Inspection requested via web by Brian Carlisle
FIR20-00403 INSP-Sprinkler Rough-in7/20/20207/23/20207/23/2020 9:06:11 AMAPASS
Rough to cover inspection for area of work complete, approved for cover.

Phone #: ###-#### Inspection requested via web by Brian Carlisle
FIR20-00402 INSP-Sprinkler Rough-in7/20/20207/23/20207/23/2020 9:05:36 AMAPASS
Rough to cover inspection for area of work complete, approved for cover.

Phone #: ###-#### Inspection requested via web by Brian Carlisle
FIR20-00380 INSP-Final Inspection7/22/20207/23/20207/23/2020 8:02:08 AMACANC
Phone #: ###-#### >> Inspection requested via web by Fire Scheduler Inspection cancelled from web by: Fire Scheduler
FIR19-00491 INSP-Final Inspection7/22/20207/23/20207/22/2020 2:22:26 PMAPASS
Previously noted item has been corrected, final inspection for scope of work is complete.

Hi Jim,

This request for final is for the wall mount PIV we spoke about.

Thanks,

Jason Phone #: ###-#### Inspection requested via web by Jason Heath