Inspections for the day of: Thursday, July 23, 2020.
Number of inspections: 21
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTell Riley
TitleBLD-COM/RES INSPECTOR
Phone #830-2752
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-00556 BLD-Final7/22/20207/23/20207/23/2020 4:41:45 PMPFAIL
Damon - */Screened*/ Phone #: ###-####//need to have hard surface turnaround per plans or provide approval from zoning//currently only a 20 foot drive connected to common driveway//
BLD19-00556 BLD-Blower Door Test Results7/23/20207/23/20207/23/2020 4:19:23 PMPDONE
5.9 ACH 50
BLD19-04651 BLD-Blower Door Test Results7/23/20207/23/20207/23/2020 4:17:16 PMPNR
BLD19-04651 BLD-Final7/22/20207/23/20207/23/2020 4:16:58 PMPNR
Damin *screened* Phone #: ###-####
BLD19-04773 BLD-Framing/Rough-in7/23/20207/23/20207/23/2020 3:39:01 PMPPART
framing/foam seal Phone #: ###-#### Inspection requested via web by Shane Shade//see Crystal and Shane onsite for list of corrections//ok to insulate in areas not affected by corrections//
BLD19-04772 BLD-Framing/Rough-in7/23/20207/23/20207/23/2020 3:38:38 PMPPART
framing/foam seal Phone #: ###-#### Inspection requested via web by Shane Shade//see Crystal and Shane onsite for list of corrections//ok to insulate in areas not affected by corrections//
BLD19-04770 BLD-Framing/Rough-in7/23/20207/23/20207/23/2020 3:38:19 PMPPART
framing/foam seal Phone #: ###-#### Inspection requested via web by Shane Shade//see Crystal and Shane onsite for list of corrections//ok to insulate in areas not affected by corrections//
BLD19-04767 BLD-Framing/Rough-in7/23/20207/23/20207/23/2020 3:37:57 PMPPART
Framing/foam seal Phone #: ###-#### Inspection requested via web by Shane Shade//see Crystal and Shane onsite for list of corrections//ok to insulate in areas not affected by corrections//
BLD20-01673 BLD-Footing7/23/20207/23/20207/23/2020 3:28:02 PMPFAIL
screened // Michael Phone #: ###-####//need approved plans onsite for inspection//will need to sleeve the sewer line through both footings//
BLD19-00535 BLD-Wall Bracing7/23/20207/23/20207/23/2020 2:53:03 PMPPASS
Interior gype shear walls all floors . Phone #: ###-#### Inspection requested via web by Lee Scott//nailing ok on interior shear walls//
BLD20-00225 BLD-Framing/Rough-in7/23/20207/23/20207/23/2020 2:52:19 PMPPASS
Vinny- */Screened*/ Phone #: ###-####//ok to insulate//
BLD20-00337 BLD-Concrete7/23/20207/23/20207/23/2020 1:07:06 PMPPART
Chase *screened* Phone #: ###-####//last of area A slab, ok pending special inspections//east part of area B slab, vapor barrier ok, no wire mesh installed yet--pend specials//
BLD20-01097 BLD-Wall Bracing7/23/20207/23/20207/23/2020 12:30:17 PMPNR
Add hot dip nails at all pt plate//nail blocking on shear locations and to top plates//
BLD20-01097 BLD-Framing/Rough-in7/22/20207/23/20207/23/2020 12:29:25 PMPCANC
screened // Leslie Phone #: ###-####//NR needs wall bracing//
BLD20-00344 BLD-Ceiling Grid Inspection7/22/20207/23/20207/23/2020 11:40:20 AMAPART
Request to lay ceiling tiles in areas with passed overhead inspections Phone #: ###-#### Inspection requested via web by Miles Gastil//ok to cover grid in phase one//
BLD20-01333 BLD-Wall Bracing7/23/20207/23/20207/23/2020 11:39:12 AMPPART
add staples in areas as discussed//add hot dipped nails to pt//ok to wrap when above complete//
BLD20-01333 BLD-Framing/Rough-in7/22/20207/23/20207/23/2020 11:38:14 AMPNR
As early as possible Phone #: 2086956570 >> Inspection requested via mobile web by Matt Swenson//needed wall bracing not framing//
BLD20-01018 BLD-Framing/Rough-in7/22/20207/23/20207/23/2020 11:13:31 AMANR
ok with video or photo // Jim Phone #: ###-####//need electrical roughed in and inspected//mechanical needs roughed in and inspected//provide truss detail for connections to girders//
BLD19-00535 BLD-Other7/22/20207/23/20207/23/2020 10:39:53 AMAPART
Ok to cover drop ceilings levels 1 and 2 . Phone #: ###-#### Inspection requested via web by Lee Scott//drops ok to cover//lee will verify that mechanical is fire caulked on floor 2 and fire sprinkler mains into riser room are fire caulked//
BLD20-01529 BLD-Framing/Rough-in7/22/20207/23/20207/23/2020 10:03:53 AMAPASS
screened // Forrest Phone #: ###-####//no new penetrations in 2hr floor above--all penetrations are existing//demising walls will be patched where cut//trades approvals ok//will need grid cover inspection for back stock room area//
BLD20-02082 BLD-Wall Bracing7/22/20207/23/20207/23/2020 9:08:49 AMAPART
thank you Phone #: ###-#### Inspection requested via web by Dean Rhodes//existing let in bracing was left//only one wall reframed and this will meet prescirptive wall bracing requirements//other areas are all sheathed as fiber board was removed due to damage//add PT or rot resist sill at new framed wall--will check at framing//