FIR00-00405
| INSP-Sprinkler Rough-in/Hydro | 7/23/2001 | 7/24/2001 | 7/24/2001 12:00:00 AM | A | PASS |
|
|
Rick ###-#### hydro on 1st floor west system okay. requested plans for the retail spaces on first floor 7/24/2001 11:37:24 AM
|
BLD01-00300
| FIRE-Final Inspection | 7/24/2001 | 7/24/2001 | 7/24/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/24/2001 at 06:44:29. Contact: ###-####.
|
BLD00-00081
| FIRE-Final Inspection | 7/24/2001 | 7/24/2001 | 7/24/2001 12:00:00 AM | A | FAIL |
|
|
Added by Inspector: 409 On 7/24/2001 9:58:43 AM penetration from sink drain into enclosure; sprinklers required; smoke seals on doors; requested sprinkler and alarm plans for 1-2-3rd floor remodels
|
BLD01-01349
| FIRE-Final Inspection | 7/24/2001 | 7/24/2001 | 7/24/2001 12:00:00 AM | P | FAIL |
|
|
Added by Inspector: 409 On 7/24/2001 3:40:25 PM plywood walls; emergency lighting; exit signs and alarm problems
|
FIR01-00328
| INSP-Final Inspection | 7/23/2001 | 7/24/2001 | 7/24/2001 12:00:00 AM | P | FAIL |
|
|
###-#### c/n issued 7/24/2001 3:40:42 PM
|
FIR01-00305
| INSP-Sprinkler Rough-in/Hydro | 7/24/2001 | 7/24/2001 | 7/24/2001 12:00:00 AM | P | PASS |
|
|
sam ###-#### underground and overhead hydro test okay 7/24/2001 10:41:26 AM
|
FIR01-00348
| INSP-Conference | 7/24/2001 | 7/24/2001 | 7/24/2001 12:00:00 AM | P | PASS |
|
|
###-#### storage not over 20 ft; heads installed at 15 ft level on 48 columns 7/24/2001 3:41:26 PM
|