PLM09-00991
| PLM-Aging Inspection | 7/24/2014 | 7/24/2014 | 7/25/2014 8:22:04 AM | | PASS |
|
|
|
PLM14-00543
| PLM-Aging Inspection | 7/24/2014 | 7/24/2014 | 7/25/2014 8:21:01 AM | | PASS |
|
|
|
PLM14-02050
| Storm Drains | 7/24/2014 | 7/24/2014 | 7/24/2014 4:54:38 PM | P | PART |
|
|
Please call Gary Tamez ###-####. Phone #: ###-#### >> Inspection requested via web by Dawn Brubaker north side storm drain,s test ok
|
PLM14-02098
| Groundwork | 7/24/2014 | 7/24/2014 | 7/24/2014 1:50:01 PM | P | PASS |
|
|
please call Cameron with any questions ###-#### >> Inspection requested via web by Ed Davis
|
PLM14-00208
| Final | 7/24/2014 | 7/24/2014 | 7/24/2014 1:10:40 PM | P | PASS |
|
|
>> Inspection requested via web by David Salamon
|
PLM14-01000
| Plumbing Rough-in | 7/24/2014 | 7/24/2014 | 7/24/2014 1:10:13 PM | P | NR |
|
|
>> Inspection requested via web by David Salamon not ready contractor will recall when ready
|
PLM14-01716
| Final | 7/24/2014 | 7/24/2014 | 7/24/2014 12:45:48 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Amanda Drake note- no sign off card on site
|
PLM13-01529
| Final | 7/24/2014 | 7/24/2014 | 7/24/2014 12:31:48 PM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Hurren
|
PLM13-01529
| Plumbing Rough-in | 7/24/2014 | 7/24/2014 | 7/24/2014 12:31:20 PM | P | PART |
|
|
rough-in on west side of building test ok contractor to recall when east side is ready
|
PLM13-01515
| Water and/or Sewer | 7/23/2014 | 7/24/2014 | 7/24/2014 12:28:17 PM | A | PASS |
|
|
swapped two water lines for 1 1/4" Phone #: ###-#### >> Inspection requested via web by Ashleigh Meligan
|
PLM14-01350
| Final | 7/22/2014 | 7/24/2014 | 7/24/2014 12:27:20 PM | A | PASS |
|
|
Please call Tori before you go. ###-#### Phone #: ###-#### >> Inspection requested via web by Mary LaFayette
|
PLM14-02126
| Groundwork | 7/23/2014 | 7/24/2014 | 7/24/2014 11:22:47 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Nels Moore
|
PLM14-02125
| Water and/or Sewer | 7/23/2014 | 7/24/2014 | 7/24/2014 10:39:14 AM | A | PART |
|
|
Phone #: ###-#### >> Inspection requested via web by Ashleigh Meligan sewer only test ok ok to cover
|
PLM13-00796
| Final | 7/23/2014 | 7/24/2014 | 7/24/2014 10:37:56 AM | A | PART |
|
|
Phone #: ###-#### >> Inspection requested via web by PATTY KIRK need 120 degree hot water limitation to restroom laves need to have two RP tested and certified for final call contractor will recall when ready
|
PLM14-01952
| Final | 7/23/2014 | 7/24/2014 | 7/24/2014 10:16:55 AM | A | FAIL |
|
|
Cathy Phone #: ###-#### correct reverse grade on tub drain repipe pvc drain to washer with approved directional drain fitting support pvc piping every 4 feet need 18 inches of metalic piping on water heater talked with owner on site will recall when ready
|
PLM14-02111
| Water and/or Sewer | 7/23/2014 | 7/24/2014 | 7/24/2014 9:15:54 AM | A | PASS |
|
|
Jeff Stevens is the project superintendant and the number attached is his. He will have the services ready for inspection in the early AM of July 24th Phone #: ###-#### >> Inspection requested via web by Bruce Scott
|
PLM14-02111
| DOC - Permit Finaled | 7/24/2014 | 7/24/2014 | 7/24/2014 9:15:41 AM | A | PASS |
|
|
Jeff Stevens is the project superintendant and the number attached is his. He will have the services ready for inspection in the early AM of July 24th Phone #: ###-#### >> Inspection requested via web by Bruce Scott
|
PLM14-02115
| Water and/or Sewer | 7/23/2014 | 7/24/2014 | 7/24/2014 9:00:30 AM | A | PASS |
|
|
please call Rick when inspected Phone #: ###-#### >> Inspection requested via web by Richard Kirk
|
PLM14-02115
| DOC - Permit Finaled | 7/24/2014 | 7/24/2014 | 7/24/2014 9:00:15 AM | A | PASS |
|
|
please call Rick when inspected Phone #: ###-#### >> Inspection requested via web by Richard Kirk
|
PLM14-01568
| Final | 7/23/2014 | 7/24/2014 | 7/24/2014 8:11:26 AM | A | PASS |
|
|
Lock box# 2267 Phone #: ###-#### >> Inspection requested via web by Troy Woolston
|