PLM18-02313
| Water and/or Sewer | 7/24/2018 | 7/24/2018 | 7/24/2018 4:44:54 PM | P | PART |
|
|
test on the rain drain heading west out of the shop ok, sewer test from interceptor to tie in ok, start 24 hour interceptor test, as it sits the water level is about 1 inch below outlet in tank, tank needs the dip tubes installed.
|
PLM17-04759
| Plumbing Rough-in | 7/24/2018 | 7/24/2018 | 7/24/2018 4:44:16 PM | P | PART |
|
|
Phone #: ###-#### Inspection requested via web by julio sagrero washer ri ok 1st through 4th
|
PLM18-03120
| Plumbing Rough-in | 7/24/2018 | 7/24/2018 | 7/24/2018 4:11:00 PM | P | PART |
|
|
RYAN IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER in wall only
|
PLM17-04139
| PLM-Aging Inspection | 7/24/2018 | 7/24/2018 | 7/24/2018 3:22:37 PM | | PEND |
|
|
|
PLM18-02754
| Water and/or Sewer | 7/23/2018 | 7/24/2018 | 7/24/2018 3:22:04 PM | A | CANC |
|
|
Christina Phone #: ###-#### this was a ri, the owner didn't do the work, Cooper plumbing did the work, the owner can get a refund if they ask and Cooper will pull a permit, needs a cleanout under the lavs.
|
PLM18-00325
| Other | 7/24/2018 | 7/24/2018 | 7/24/2018 2:55:06 PM | P | PEND |
|
|
dishwasher needs an rp
|
PLM18-03124
| Water and/or Sewer | 7/24/2018 | 7/24/2018 | 7/24/2018 2:26:09 PM | P | CANC |
|
|
Dale-partial Phone #: ###-#### called and canceled
|
PLM18-01017
| Pressure Test | 7/24/2018 | 7/24/2018 | 7/24/2018 2:01:07 PM | P | PASS |
|
|
Flue pressure test for tankless water heater, roof drains water test Phone #: ###-#### Inspection requested via web by Pat Falls 5# water heater flue and roof drain test ok.
|
PLM18-02404
| Final | 7/23/2018 | 7/24/2018 | 7/24/2018 11:39:03 AM | A | PASS |
|
|
Ready for any time mait Phone #: ###-#### Inspection requested via web by j mait downer jr
|
PLM17-04740
| Final | 7/23/2018 | 7/24/2018 | 7/24/2018 11:39:03 AM | A | PASS |
|
|
CHRIS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
PLM18-03123
| Final | 7/24/2018 | 7/24/2018 | 7/24/2018 11:15:04 AM | P | PART |
|
|
Please give me a call with any questions and access directions Phone #: ###-#### Inspection requested via web by Kelly King public restrooms floors 2,3,10 and 12 trimmed out.
|
PLM18-03108
| Groundwork | 7/23/2018 | 7/24/2018 | 7/24/2018 8:13:07 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by casey lattimergw and tied to existing sewer stub to building ok
|
PLM18-02680
| Final | 7/23/2018 | 7/24/2018 | 7/24/2018 8:03:07 AM | A | PASS |
|
|
Please call Ed at ###-#### to coordinate Phone #: ###-#### Inspection requested via web by Dawn Kalsbeek ri ok
|
PLM17-03351
| PLM-Aging Inspection | 7/24/2018 | 7/24/2018 | 7/24/2018 7:33:45 AM | | PEND |
|
|
|
PLM18-01235
| Final | 7/23/2018 | 7/24/2018 | 7/23/2018 3:32:49 PM | A | PASS |
|
|
Ready Now - for access call Ryan Parker to meet you onsite ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
PLM18-02907
| Groundwork | 7/23/2018 | 7/24/2018 | 7/23/2018 2:58:04 PM | A | PASS |
|
|
Please call Brad at ###-#### prior to inspection for access to building. He will meet inspector at the site. Phone #: ###-#### Inspection requested via web by TIM OVERALL gw and interceptor and trench drain ok to cover
|