BLD17-02975
| FIRE-Final Inspection | 7/23/2018 | 7/24/2018 | 7/24/2018 2:48:08 PM | P | PASS |
|
|
life safety passed.
Tony Phone #: ###-####
|
NAF18-00049
| INSP-Final | 7/23/2018 | 7/24/2018 | 7/24/2018 2:11:47 PM | P | FAIL |
|
|
Not ready for final yet. Need tape removed from uprights in the Cafeteria and Restrooms, need pendant heads installed shown on plans in the Dry Storage Room, need verification of combustible concealed space coverage over the existing kitchen. Hydro test passed for the new Kitchen area.
Call prior to going Phone #: 2088901055 >> Inspection requested via mobile web by Zack Grasmick
|
BLD18-02461
| FIRE-Final Inspection | 7/23/2018 | 7/24/2018 | 7/24/2018 1:44:54 PM | A | PASS |
|
|
The wrong hardware was installed on the door. Crystal stated she will have passage hardware installed prior the the building inspection. Life safety passed.
Crystal Phone #: ###-####
|
BLD18-02507
| FIRE-Final Inspection | 7/23/2018 | 7/24/2018 | 7/24/2018 1:42:43 PM | A | CANC |
|
|
I was unable to make it to the inspection at the same time as the tenant. I rescheduled it for tomorrow morning.
Please call ahead for access - Sevana Phone #: ###-####
|
FIR15-00822
| INSP-Final Inspection | 7/23/2018 | 7/24/2018 | 7/24/2018 12:31:32 PM | A | PASS |
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00559
| INSP-Final Inspection | 7/23/2018 | 7/24/2018 | 7/24/2018 12:29:40 PM | A | PASS |
|
|
Permit finaled
John Phone #: ###-####
|
FIR17-00507
| INSP-Supply line flush | 7/23/2018 | 7/24/2018 | 7/24/2018 11:38:21 AM | A | PASS |
|
|
Underground flush passed. We pito tested and verified flow required for remote area.
IF possible can we get the flush around 11 am? Phone #: ###-#### Inspection requested via web by Stan Beus
|
BLD10-00352
| FIRE-Final Inspection | 7/23/2018 | 7/24/2018 | 7/24/2018 10:19:34 AM | A | FAIL |
|
|
Tenant did not have any of the review notes or small documents. The plan they had I was unable to verifiy if it was approved since the stamp location was not legible. However the racking layout, as shown on the plans, did not match what has been installed. I deferred him to plan review to submit a revised plans and request all small documents. Also the scope of work states 10' racking but the fire review notes state 12' racks and 12' max storage.
Phone #: 1-###-####
|
FIR18-00496
| INSP-Final Inspection | 7/23/2018 | 7/24/2018 | 7/24/2018 9:33:33 AM | A | FAIL |
|
|
Devices as installed passed inspection but the new devices sound at temporal where as the existing devices are a solid tone. As discussed the contractor/owner will need to contact the Boise Fire Dept about a possible upgrade agreement to bring the existing devices into code compliance.
Ray McQueen, inspecting technician. Building access is open. Phone #: ###-#### Inspection requested via web by Rose Peterson
|
FIR18-00395
| INSP-Final Inspection | 7/20/2018 | 7/24/2018 | 7/24/2018 9:19:16 AM | A | FAIL |
|
|
No actual testing was performed today. We did however perform a walk through and I noted strobes that are overspaced and acouple that are nmissing. There is a restroom in the northwest corner of the building that needs notification. There is a strobe in a restroom that is not shown on the plans. Several trobes are mounted too low. Several pull stations are mounted too high. As-builts need to be submitted. Plan reviewer may require plan modifications. See the city approved plans for corrections marked in red ink.
Requesting an Early inspection at 7:00 due to Businesses operating hours, please. Phone #: ###-#### Inspection requested via web by David Oliver
|
FIR18-00012
| INSP-Supply line flush | 7/23/2018 | 7/24/2018 | 7/24/2018 9:15:11 AM | A | PASS |
|
|
Underground flush of the three supplies in the breeze way passed.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00548
| INSP-Sprinkler Rough-in | 7/23/2018 | 7/24/2018 | 7/24/2018 9:14:13 AM | A | PART |
|
|
First, second and third floor piping rough-in passed. Piping can be covered. Tenting for third floor piping passed. The only piping that can not be covered is the 2" risers at the third floor since they have not been "caped" as discussed to protect the piping from freezing.
OVerhead RTC Phone #: ###-#### Inspection requested via web by Stan Beus
|