Inspections for the day of: Wednesday, July 25, 2007.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD07-00529 FIRE-Final Inspection7/25/20077/25/20077/27/2007 5:10:03 PMPPASS
Fire life safety passed inspection.
BLD07-00531 FIRE-Final Inspection7/25/20077/25/20077/27/2007 1:50:13 PMPPASS
Fire life safety is satisfactory, inspection passed.
BLD07-01644 FIRE-Conference7/24/20077/25/20077/27/2007 1:41:58 PMADONE
On site visit to discuss project related fire alarm and sprinkler permit issues.
FIR07-00106 INSP-Conference7/24/20077/25/20077/25/2007 4:35:37 PMPPART
Completed pump acceptance testing per NFPA 20, noted some items in need of correction including mesh at PRV and engine exhaust discharge, FDC needs repair, lock fuel supply open, no galvanized pipe is allowed in the fuel supply line, pump room needs adequate ventilation and a floor drain, provide 3-way valve at jockey sensing guage, tighten bolts at flex exhaust flange, program weekly run timer, the pressure limiting device solenoid is not functioning properly. Pump curve data meets requirements.
FIR07-00540 INSP-Final Inspection7/25/20077/25/20077/25/2007 4:29:02 PMPPART
Final pending as-built plans for field modifications, also need to test door holder interconnections when completed, provide updated map at the panel.
FIR07-00554 INSP-Final Inspection7/24/20077/25/20077/25/2007 1:36:19 PMPCANC
No time available to complete this inspection today.
BLD07-01475 FIRE-Final Inspection7/23/20077/25/20077/25/2007 1:35:25 PMANR
Need project related fire sprinkler permit final prior to life safety final.
FIR07-00502 INSP-Sprinkler Rough-in7/24/20077/25/20077/25/2007 1:04:30 PMAPART
UG fire supply line installation is good for cover.
FIR07-00220 INSP-Sprinkler Rough-in7/24/20077/25/20077/25/2007 12:40:18 PMAPART
Rough-in is approved for cover, final pending ceilng tile and escutcheons.
FIR07-00520 INSP-Sprinkler Rough-in7/24/20077/25/20077/25/2007 12:38:58 PMAPART
Okay for cover at the drop ceilings, noted one hanger that has been removed to be re-installed.
FIR06-00540 INSP-Sprinkler Rough-in/Hydro7/24/20077/25/20077/25/2007 12:02:02 PMAPART
OH hydrostatic test for the 5th floor SW quad passed.
FIR07-00573 INSP-Final Inspection7/19/20077/25/20077/25/2007 11:34:46 AMPCANC
dave Phone #: ###-#### Inspection cancelled from web by: Victoria Apatang
FIR07-00038 FIR-Aging Inspection7/25/20077/25/20077/25/2007 11:23:10 AM DEFR
Work in progress
FIR07-00244 INSP-Final Inspection7/23/20077/25/20077/25/2007 11:21:47 AMANR
Need shell and core project final prior to tenant permit final request.
FIR06-00704 INSP-Final Inspection7/23/20077/25/20077/25/2007 11:20:25 AMACANC
No time available to complete inspection.
BLD06-00688 FIRE-Final Inspection7/20/20077/25/20077/25/2007 11:19:44 AMACANC
No time available to complete inspection.
FIR07-00280 INSP-Sprinkler Rough-in/Hydro7/25/20077/25/20077/25/2007 11:16:18 AMAPART
Preaction system passed 24 hr. air test.
FIR07-00545 INSP-Sprinkler Rough-in7/24/20077/25/20077/25/2007 11:15:08 AMAPART
OH rough-in is approved for cover at the drop ceilings.
FIR07-00556 INSP-Final Inspection7/23/20077/25/20077/25/2007 11:13:55 AMAPASS
Fire alarm work passed field inspection, permit finaled.
FIR07-00203 INSP-Final Inspection7/18/20077/25/20077/18/2007 9:42:17 AMACANC
PUMP TEST. PLEASE CALL JEFF PACKHAM IF THERE ARE QUESTIONS. Phone #: ###-#### Internet Inspection Request from: Jeff Packham Inspection cancelled from web by: Jeff Packham