BLD13-01766
| BLD-Framing/Rough-in | 7/25/2013 | 7/25/2013 | 7/25/2013 3:40:36 PM | P | NH |
|
|
josiah Phone #: ###-####. no one home.
|
BLD13-01075
| BLD-Foundation | 7/24/2013 | 7/25/2013 | 7/25/2013 3:32:58 PM | P | PART |
|
|
JOE Phone #: ###-####.
|
BLD13-01288
| BLD-Conference | 7/24/2013 | 7/25/2013 | 7/25/2013 3:01:12 PM | P | PART |
|
|
Walk through for framing inspection. Recieved the 1hr. floor ceiling assembly for the roseburg RFPI joist being used on the project. Will have scanned in. Will be using joist on all buildings.
|
BLD13-01395
| BLD-Framing/Rough-in | 7/25/2013 | 7/25/2013 | 7/25/2013 2:27:45 PM | P | PASS |
|
|
Larry Phone #: ###-####. Interior wood framed walls, exterior wall infill and new gargage door opening.
|
BLD13-01950
| BLD-Final | 7/24/2013 | 7/25/2013 | 7/25/2013 11:07:54 AM | A | DONE |
|
|
>> Inspection requested via web by Richard Murray
|
BLD13-01950
| DOC - Permit Finaled | 7/25/2013 | 7/25/2013 | 7/25/2013 11:07:35 AM | P | PASS |
|
|
|
BLD13-01594
| BLD-Other | 7/24/2013 | 7/25/2013 | 7/25/2013 10:16:50 AM | A | NR |
|
|
mike - rebar Phone #: ###-####. eeds to provide the approved plans.
|
ESC13-00353
| Random Inspection | 7/25/2013 | 7/25/2013 | 7/25/2013 10:02:44 AM | A | PASS |
|
|
|
BLD13-00921
| BLD-Energy code compliance | 7/24/2013 | 7/25/2013 | 7/25/2013 10:00:18 AM | A | PASS |
|
|
Jeff Phone #: ###-####
|
ESC13-00430
| Site Preparation | 7/25/2013 | 7/25/2013 | 7/25/2013 9:28:50 AM | A | PASS |
|
|
|
BLD13-01154
| BLD-Footing | 7/24/2013 | 7/25/2013 | 7/25/2013 9:28:21 AM | A | PASS |
|
|
doug Phone #: ###-####
|
GCB12-00143
| GCB-Final | 7/25/2013 | 7/25/2013 | | P | |
|
|
Odie ###-####
|