BLD17-00143
| BLD-Aging Inspection | 7/25/2018 | 7/25/2018 | 7/26/2018 4:51:15 PM | | PEND |
|
|
|
BLD17-03809
| BLD-Aging Inspection | 7/25/2018 | 7/25/2018 | 7/26/2018 4:50:14 PM | | PEND |
|
|
|
BLD17-02497
| BLD-Aging Inspection | 7/25/2018 | 7/25/2018 | 7/26/2018 4:49:51 PM | | PASS |
|
|
|
MIS18-00268
| BLD-Conference | 7/24/2018 | 7/25/2018 | 7/26/2018 4:48:44 PM | P | PEND |
|
|
follow up
|
BLD17-02032
| BLD-Conference | 7/24/2018 | 7/25/2018 | 7/25/2018 4:09:05 PM | A | NR |
|
|
Please call to let him know if he passed // Rob Phone #: ###-####/// take plan review out to site
|
BLD18-01859
| BLD-Footing | 7/24/2018 | 7/25/2018 | 7/25/2018 4:08:07 PM | P | PEND |
|
|
Phone #: 2085736921 >> Inspection requested via mobile web by Jimmy,, ok pending soils approval
|
BLD18-02179
| BLD-Footing | 7/25/2018 | 7/25/2018 | 7/25/2018 4:06:16 PM | P | PART |
|
|
Derik Phone #: ###-####,, ok to add rebar and bidge over protected sewer line for now until it gets moved,, work in progress,, garage ok also
|
BLD18-01094
| BLD-Other | 7/25/2018 | 7/25/2018 | 7/25/2018 3:18:16 PM | P | PASS |
|
|
Foam seal // Richard Phone #: ###-####
|
BLD18-02527
| BLD-Footing | 7/25/2018 | 7/25/2018 | 7/25/2018 3:10:14 PM | P | PASS |
|
|
Jose Phone #: ###-####,, basement footing, storage only
|
BLD18-02207
| BLD-Footing | 7/25/2018 | 7/25/2018 | 7/25/2018 3:09:09 PM | P | PART |
|
|
Matt Phone #: ###-####,, monolithic ok,, work in progress
|
BLD17-01998
| BLD-Conference | 7/25/2018 | 7/25/2018 | 7/25/2018 2:55:32 PM | P | PART |
|
|
Virgil-owner says it''s not an ADU-please verify Phone #: ###-####-please call an hour prior to meet-go through garage,, not beyond the scope of work at this time,, no plans on site
|
MIS18-00017
| DOC - Permit Expired | 7/25/2018 | 7/25/2018 | 7/25/2018 2:53:36 PM | P | PASS |
|
|
|
BLD18-02046
| BLD-Framing/Rough-in | 7/24/2018 | 7/25/2018 | 7/25/2018 2:51:26 PM | A | PASS |
|
|
Bob Phone #: ###-####
|
BLD17-01917
| BLD-Final | 7/24/2018 | 7/25/2018 | 7/25/2018 12:11:53 PM | A | DONE |
|
|
Final Phone #: ###-#### Inspection requested via web by Joshua Adams
|
BLD17-01917
| DOC - Permit Finaled | 7/25/2018 | 7/25/2018 | 7/25/2018 12:11:47 PM | P | PASS |
|
|
done
|
BLD18-01959
| BLD-Foundation | 7/24/2018 | 7/25/2018 | 7/25/2018 12:11:10 PM | A | PART |
|
|
Javier Phone #: ###-####,, work in progress, ok,,
|
BLD17-01970
| BLD-Framing/Rough-in | 7/24/2018 | 7/25/2018 | 7/25/2018 11:58:29 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD18-01762
| BLD-Energy code compliance | 7/24/2018 | 7/25/2018 | 7/25/2018 11:40:48 AM | A | PASS |
|
|
Bobby Phone #: ###-####
|
BLD17-03575
| BLD-Energy code compliance | 7/24/2018 | 7/25/2018 | 7/25/2018 11:39:30 AM | A | PASS |
|
|
Thank you!! Phone #: ###-#### Inspection requested via web by Nancy Frost
|
BLD18-00820
| BLD-Framing/Rough-in | 7/24/2018 | 7/25/2018 | 7/25/2018 9:17:51 AM | A | PASS |
|
|
Maita Phone #: ###-####,, ok to insulate
|
MIS18-00249
| BLD-Conference | 7/18/2018 | 7/25/2018 | 7/24/2018 4:16:55 PM | A | PEND |
|
|
doing work without permits on multi-fam building. Tearing out walls, moving walls, etc. // STATUS REVIEW,, still in review
|