BLD99-00978
| INSP - Framing/Rough-in | 7/26/1999 | 7/26/1999 | 7/27/2000 12:00:00 AM | P | PART |
|
|
07/26/99 340 - part, furring & partitions ok to insul.
|
BLD99-01547
| INSP - Foundation | 7/23/1999 | 7/26/1999 | 7/27/1999 12:00:00 AM | P | FAIL |
|
|
07/26/99 340 - CURTIS ###-####; poured w/o insp. c/n, need eng's ok. not
|
BLD99-01018
| INSP - Final | 7/26/1999 | 7/26/1999 | 7/26/1999 12:00:00 AM | | PART |
|
|
/ / 340 - CONF ONLY RE FINAL REQ'S...OK FOR T/O
|
BLD98-00643
| INSP - Framing/ Rough-in | 7/26/1999 | 7/26/1999 | 7/26/1999 12:00:00 AM | | PART |
|
|
/ / 340 - NO INSP; FRAME OK PER 338, WILL MAKE ENTRY
|
BLD98-03382
| INSP - Final | 7/23/1999 | 7/26/1999 | 7/26/1999 12:00:00 AM | A | FAIL |
|
|
07/26/99 340 - Gary ###-####; need fire & access above lid, c/n
|
BLD99-00161
| INSP - Final | 7/23/1999 | 7/26/1999 | 7/26/1999 12:00:00 AM | A | PASS |
|
|
07/26/99 340 - MIKE ###-####; ok card to contractor
|
BLD99-00162
| INSP - Final | 7/23/1999 | 7/26/1999 | 7/26/1999 12:00:00 AM | A | PASS |
|
|
07/26/99 340 - MIKE ###-####; card to contractor
|
BLD99-00280
| INSP - Framing/Rough-in | 7/23/1999 | 7/26/1999 | 7/26/1999 12:00:00 AM | A | FAIL |
|
|
07/26/99 340 - fire shafts Rob ###-####; c/n, need listing for "fire tap
|
BLD99-00681
| INSP - Framing/Rough-in | 7/23/1999 | 7/26/1999 | 7/26/1999 12:00:00 AM | A | PART |
|
|
07/26/99 340 - Jim ###-####; add 2nd layer gyp thru-out at corridor.
|
BLD99-00975
| INSP - Framing/Rough-in | 7/23/1999 | 7/26/1999 | 7/26/1999 12:00:00 AM | A | PART |
|
|
07/26/99 340 - LEON ###-####; south corridor frame ok to cover, add fire
|
BLD99-00774
| INSP - Framing/Rough-in | 7/26/1999 | 7/26/1999 | 7/26/1999 12:00:00 AM | P | PART |
|
|
07/26/99 340 - ceiling Chuck ###-####
|
BLD99-01614
| INSP - Final | 7/26/1999 | 7/26/1999 | 7/26/1999 12:00:00 AM | P | FAIL |
|
|
07/26/99 340 - scott ###-#### billboard (better if set up appt.) has CUP
|