Inspections for the day of: Tuesday, July 26, 2016.
Number of inspections: 19
Percentage of inspections complete: 95 %
Percentage of inspections not complete: 5 %
Contact Information
InspectorMike Jordan
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD16-02454 BLD-Final7/21/20167/22/2016 P 
Pierre Phone #: ###-####
BLD15-04500 BLD-Energy code compliance7/26/20167/26/20167/26/2016 4:17:56 PMPPASS
Phone #: ###-#### Inspection requested via web by joey benart
BLD15-04472 BLD-Footing7/26/20167/26/20167/26/2016 3:59:26 PMPPASS
Phone #: ###-#### Inspection requested via web by Michael West. Bldg 1 footing on gridline b from grids 1 to 5 and on gridline 1 from grids a to E. also elevator pit floor ok. Work in progress on south footings, ok to place when special inspection has passed.
BLD16-01108 BLD-Wall Bracing7/26/20167/26/20167/26/2016 2:45:33 PMPPASS
Chad Phone #: ###-####
BLD16-01107 BLD-Wall Bracing7/26/20167/26/20167/26/2016 2:45:20 PMPPASS
Chad Phone #: ###-####
BLD16-01801 BLD-Framing/Rough-in7/26/20167/26/20167/26/2016 2:07:15 PMPNR
or ###-#### Jerry Phone #: ###-####. Needs electrical rough in inspection and complete airseal package.
ESC16-00814 Site Final7/26/20167/26/20167/26/2016 1:54:59 PMPDONE
ESC16-00814 DOC - Permit Finaled7/26/20167/26/20167/26/2016 1:54:41 PMPPASS
BLD16-01583 BLD-Final7/26/20167/26/20167/26/2016 1:53:43 PMPPASS
Tim Phone #: ###-####
BLD16-01583 DOC - Permit Finaled7/26/20167/26/20167/26/2016 1:53:12 PMPPASS
BLD16-01583 BLD-Framing/Rough-in7/26/20167/26/20167/26/2016 1:52:24 PMPPASS
Tim Phone #: ###-####
BLD16-01525 BLD-Conference7/25/20167/26/20167/26/2016 10:45:50 AMADONE
Reviewed footing and foundation plan and awnsered questions regarding interior column pad footings and thickend slab footings.
BLD16-01039 BLD-Wall Bracing7/26/20167/26/20167/26/2016 9:55:32 AMAPASS
Shear inspection, plans on site Inspection requested via web by Erby Gonzales
BLD15-03493 BLD-Footing7/25/20167/26/20167/26/2016 9:25:32 AMAFAIL
Jason Phone #: ###-####. North footing not the rquired 1ft in depth. Missing the 4 #5 rebar in east footing, also needs to raise reinforcement in footings to obtain the minimum 3 inch clearance from the ground.
BLD16-01129 BLD-Final7/25/20167/26/20167/26/2016 8:38:57 AMAFAIL
Phone #: 2085015747 >> Inspection requested via mobile web by Thomas Lane. Need final for fire place, banaster for stairs not completed.
ESC16-00472 Site Final7/26/20167/26/20167/26/2016 8:32:42 AMADONE
ESC16-00472 DOC - Permit Finaled7/26/20167/26/20167/26/2016 8:32:32 AMPPASS
BLD16-01164 BLD-Final7/25/20167/26/20167/26/2016 8:31:08 AMAPASS
Phone #: 2085134849 >> Inspection requested via mobile web by Cody Walker
BLD16-01164 DOC - Permit Finaled7/26/20167/26/20167/26/2016 8:30:32 AMPPASS