MEC17-03254
| Final | 7/26/2017 | 7/26/2017 | 7/26/2017 3:28:40 PM | P | PASS |
|
|
late pm please call Chuck ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss
|
PLM17-00840
| Final | 7/26/2017 | 7/26/2017 | 7/26/2017 3:14:51 PM | P | PASS |
|
|
|
PLM17-00840
| Water and/or Sewer | 7/26/2017 | 7/26/2017 | 7/26/2017 3:12:16 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Darren Wood
|
PLM17-02759
| Plumbing Rough-in | 7/25/2017 | 7/26/2017 | 7/26/2017 2:52:52 PM | P | PASS |
|
|
Isaac-Sewer Phone #: ###-#### three sewers to new addition ok, may add roof drainage to permit
|
MEC17-03237
| Final | 7/25/2017 | 7/26/2017 | 7/26/2017 2:51:40 PM | P | PASS |
|
|
Field Super: Chad Robertson Phone #: ###-#### Inspection requested via web by Lisa Whitney
|
PLM17-02771
| Final | 7/25/2017 | 7/26/2017 | 7/26/2017 2:51:20 PM | P | PASS |
|
|
installed new 50 gallon gas heater in laundry room Phone #: ###-#### Inspection requested via web by niall magill
|
PLM17-02422
| Plumbing Rough-in | 7/26/2017 | 7/26/2017 | 7/26/2017 2:17:20 PM | P | PASS |
|
|
Casey Phone #: ###-#### ri ok
|
MEC17-02723
| Conference | 7/25/2017 | 7/26/2017 | 7/26/2017 2:06:56 PM | A | PASS |
|
|
witness duct blast 1230 pm Phone #: ###-#### Inspection requested via web by dannyel chaloupka
|
PLM17-02228
| Plumbing Rough-in | 7/26/2017 | 7/26/2017 | 7/26/2017 2:06:37 PM | P | PASS |
|
|
Casey Phone #: ###-#### Casey will send a picture of the sump vent in the floor joist with grade and cut the hub drain waste arm back to 42". ri ok
|
MEC17-02724
| Conference | 7/25/2017 | 7/26/2017 | 7/26/2017 1:13:03 PM | A | PASS |
|
|
witness duct blast 1130 am Phone #: ###-#### Inspection requested via web by dannyel chaloupka
|
MEC17-03253
| Final | 7/26/2017 | 7/26/2017 | 7/26/2017 1:03:16 PM | P | PASS |
|
|
###-#### Phone #: ###-#### Inspection requested via web by Krista Boss ri final ok
|
MEC17-03177
| Final | 7/26/2017 | 7/26/2017 | 7/26/2017 12:24:39 PM | P | PASS |
|
|
INSPECTOR WAS UNABLE TO LOCATE CO DETECTORS THAT WERE INSTALLED. OWEN OUR INSTALL MANAGER CALLED ALLEN TO NOTIFY HIM OF THAT AND PLACING BACK FOR RE-INSPECT- CALL OWEN FOR ANY QUESTIONS Phone #: ###-#### Inspection requested via web by Rick Montgomery
|
PLM17-01491
| Plumbing Rough-in | 7/25/2017 | 7/26/2017 | 7/26/2017 12:20:46 PM | P | PASS |
|
|
Inspection requested via web by Brian Johansen ri ok
|
PLM17-01493
| Plumbing Rough-in | 7/25/2017 | 7/26/2017 | 7/26/2017 12:20:16 PM | P | FAIL |
|
|
Inspection requested via web by Brian Johansen provide hard cold water to the kitchen sink
|
MEC17-02111
| Final | 7/26/2017 | 7/26/2017 | 7/26/2017 11:42:40 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by dannyel chaloupka
|
MEC16-03284
| Final | 7/21/2017 | 7/26/2017 | 7/26/2017 10:44:45 AM | A | PASS |
|
|
Call Ken 1 hour before arrival ###-#### Phone #: ###-#### Inspection requested via web by Andrea Grigsby
|
MEC17-02347
| Final | 7/24/2017 | 7/26/2017 | 7/26/2017 10:14:40 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Mary LaFayette ac ok
|
MEC17-03016
| Final | 7/19/2017 | 7/26/2017 | 7/26/2017 10:00:51 AM | A | PASS |
|
|
Please call prior to inspection Brad or Angela ###-#### Phone #: ###-#### Inspection requested via web by Mary LaFayette
|
PLM17-02501
| Groundwork | 7/25/2017 | 7/26/2017 | 7/26/2017 7:53:34 AM | A | PART |
|
|
24 hr tank test Phone #: ###-#### Inspection requested via web by Nicholas Paige start of the test on the new tank.
|
PLM17-02604
| Plumbing Rough-in | 7/25/2017 | 7/26/2017 | 7/25/2017 5:13:24 PM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Johansen Inspection cancelled from web by: Brian Johansen
|