Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC12-00206 Aging Inspection7/27/20157/27/20157/27/2015 4:11:40 PM PASS
SFH's in progress
No ESC issues observed during this time of inspection
ESC12-00403 Conference7/27/20157/27/20157/27/2015 2:11:19 PMPPEND
Phone Call to John Beck inquiring where the JUMP Project's SWPPP is. He stated he is unsure but will continue to look. I have a feeling Strata (SWPPP Developer) may have it in their office. Contacted ACHD Luke Roberts to discuss as well. Will perform an audit inspection to located their SWPPP to ensure they have been updating their SWPPP per EPA requirements, and get back into ESC Compliance with City of Boise and ACHD for contractor keeping SWPPP updated and onsite at all times.
ESC14-00783 Aging Inspection7/27/20157/27/20157/27/2015 12:40:47 PM PEND
Demo work has not begun yet
ESC13-01231 General Inspection7/27/20157/27/20157/27/2015 10:53:51 AM PASS
WIP: Interior and Exterior. No Trackout observed. No ESC issues at this time
ESC13-01167 General Inspection7/27/20157/27/20157/27/2015 10:39:41 AM PEND
80% re-vegetation of back slope of home
ESC11-00192 General Inspection7/27/20157/27/20157/27/2015 10:35:54 AM PASS
2 SFH's currently being constructed. No ESC issues observed at this time
ESC13-00193 General Inspection7/27/20157/27/20157/27/2015 10:30:26 AM PART
No Activity at time of inspection. After recent rains, curbs on Northside of culdesac needs to be swept out
ESC13-00764 Aging Inspection7/27/20157/27/20157/27/2015 10:20:33 AM PART
Sweep Sidewalks, Sweep streets again after last large rain fall
ESC13-00690 Aging Inspection7/27/20157/27/20157/27/2015 9:45:41 AM PEND
No Activity
ESC14-00689 General Inspection7/27/20157/27/20157/27/2015 9:40:48 AM PEND
re-vegetation
ESC12-00403 General Inspection7/27/20157/27/20157/27/2015 8:55:28 AM PASS
Verticle Construction in progress