ELE16-02420
| Electrical Rough-In | 7/26/2016 | 7/27/2016 | 7/27/2016 2:36:06 PM | P | PASS |
|
|
Jess Phone #: ###-#### Final ok Rough in ok to cover.. Owner will have 1in flooring down in front of panel to make main breaker meet 6ft7in rule at final
|
ELE16-02146
| Final | 7/27/2016 | 7/27/2016 | 7/27/2016 2:20:07 PM | P | PASS |
|
|
JR Phone #: ###-#### Final ok
|
ELE16-02303
| Permanent Service | 7/21/2016 | 7/27/2016 | 7/27/2016 2:00:43 PM | P | PASS |
|
|
Kyle Phone #: ###-#### p/s o/h rec ok
|
ELE15-03119
| Final | 7/27/2016 | 7/27/2016 | 7/27/2016 1:37:15 PM | P | PASS |
|
|
Jay Phone #: ###-#### Final ok
|
ELE15-03729
| Electrical Rough-In | 7/27/2016 | 7/27/2016 | 7/27/2016 12:49:09 PM | P | PART |
|
|
Partial Final Rooms 1-10 Building 2 Please call 30 minutes prior for access Phone #: ###-#### Inspection requested via web by Kerri Hamilton Patial final rooms 1-10 ok
|
ELE16-02412
| Electrical Rough-In | 7/26/2016 | 7/27/2016 | 7/27/2016 11:19:37 AM | A | PASS |
|
|
Conduit dept Insp Phone #: ###-#### Inspection requested via web by John VanZandt Underground for garage rough in ok
|
ELE16-02014
| Final | 7/26/2016 | 7/27/2016 | 7/27/2016 11:17:16 AM | A | PASS |
|
|
I will call in the morning and Schedule a time to meet you onsite Phone #: ###-#### Inspection requested via web by Matthew Dunay final ok
|
ELE16-02014
| Electrical Rough-In | 7/27/2016 | 7/27/2016 | 7/27/2016 11:11:04 AM | P | PASS |
|
|
I will call in the morning and Schedule a time to meet you onsite Phone #: ###-#### Inspection requested via web by Matthew Dunay final ok
|
ELE16-02419
| Permanent Service | 7/26/2016 | 7/27/2016 | 7/27/2016 10:17:06 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Debby Pierce p/s u/g n ok
|
ELE16-01513
| Electrical Rough-In | 7/26/2016 | 7/27/2016 | 7/27/2016 9:52:04 AM | A | PART |
|
|
Ceiling inspection in corridor where 2x2 troffers and can light frames are. Phone #: ###-#### Inspection requested via web by steve ragan ceilings ok to cover
|
ELE16-01512
| Final | 7/26/2016 | 7/27/2016 | 7/27/2016 9:50:07 AM | A | PASS |
|
|
2nd floor office space adjacent to new corridor Phone #: ###-#### Inspection requested via web by steve ragan Final ok
|
ELE16-01512
| Electrical Rough-In | 7/26/2016 | 7/27/2016 | 7/27/2016 9:48:45 AM | A | PART |
|
|
Ceiling inspection. 2nd floor office space adjacent to new corridor Phone #: ###-#### Inspection requested via web by steve ragan Ceiling only ok to cover
|
ELE15-02378
| Final | 7/26/2016 | 7/27/2016 | 7/27/2016 9:01:53 AM | A | PASS |
|
|
Vince Phone #: ###-#### Corrections made final ok
|
ELE16-02150
| Electrical Rough-In | 7/26/2016 | 7/27/2016 | 7/27/2016 8:58:47 AM | P | CANC |
|
|
Contact: Paul Wheeler, PM Ceiling inspection please Phone #: ###-#### >> Inspection requested via web by Deb Gooden Inspection cancelled from web by: Deb Gooden
|
ELE16-01897
| Final | 7/26/2016 | 7/27/2016 | 7/27/2016 8:44:55 AM | A | NR |
|
|
Phone #: ###-#### Inspection requested via web by Kerri Hamilton Not ready Call it back in
|
ELE16-02394
| Temporary Service | 7/26/2016 | 7/27/2016 | 7/27/2016 8:25:15 AM | A | PASS |
|
|
Corrections made Phone #: ###-#### Inspection requested via web by Darren Larsen t/s u/g n ok
|