ESC15-00623
| General Inspection | 7/27/2016 | 7/27/2016 | 7/28/2016 3:50:22 PM | | CANC |
|
|
|
ESC15-00731
| General Inspection | 7/27/2016 | 7/27/2016 | 7/28/2016 3:50:14 PM | | CANC |
|
|
|
ESC15-01224
| General Inspection | 7/27/2016 | 7/27/2016 | 7/28/2016 3:33:19 PM | | CANC |
|
|
|
ESC15-00931
| Site Final | 7/25/2016 | 7/27/2016 | 7/28/2016 3:32:54 PM | P | NR |
|
|
Temp BMPs still installed. Second verbal request to remove issued to Sunrise Homes
|
ESC15-00556
| General Inspection | 7/27/2016 | 7/27/2016 | 7/28/2016 3:16:51 PM | | PEND |
|
|
Crews back on site working on new phase of East Valley. Limited work occuring, no dust but dirt is very loose. Will need to requied dust removal when watered down. Restrict traffic.
Will check next week for solution. No issues currently and no complaints yet...
|
ESC15-01612
| Site Final | 7/22/2016 | 7/27/2016 | 7/28/2016 2:18:32 PM | A | NR |
|
|
Home is now complete and landscaping completed. Will monitor how the hydroseeded grass areas perform over the new few weeks. Need to sweep up loose rocks and dirt in gutter in front of home.
|
ESC16-00074
| Aging Inspection | 7/27/2016 | 7/27/2016 | 7/28/2016 9:23:20 AM | | PASS |
|
|
|
ESC16-00455
| General Inspection | 7/27/2016 | 7/27/2016 | 7/27/2016 3:05:23 PM | P | PASS |
|
|
check Crane Creek culvert work - refered by ACHD inspector
WIP. No violations. Will be replacing Crane Creek concrete cover once site work for stormwater and utilities is complete. No debris or sediment going into creek, which is at very low flow. Requested that edges of pavement around exposed portion be swept
|
ESC15-01553
| Aging Inspection | 7/27/2016 | 7/27/2016 | 7/27/2016 3:02:56 PM | | PASS |
|
|
Mill District Square townhome complete. All permits finaled. Final landscaping on some units is finishing up. Temp BMPs to be removed with last open permit closure.
|
ESC15-01553
| DOC - Permit Finaled | 7/27/2016 | 7/27/2016 | 7/27/2016 3:00:09 PM | P | PASS |
|
|
|
ESC16-01006
| Site Preparation | 7/27/2016 | 7/27/2016 | 7/27/2016 1:23:25 PM | P | PASS |
|
|
Permit sign posted on development sign off Peirce Park. Construction entrance installed on Saxton and in use, no access to Pierce Park yet. Berm protects the irrigation ditch north of the site. Once area is cleared at the PP entrance, a silt fence will be installed in between entrance and unbermed creek area. Site is very flat and should retain stormwater.
Water truck is in use for dust control. Fill up hydrant near by on Saxton.
Approved for construction. No CUP in place requiring construction fencing. Staging area does not appear to be next to home with complaints.
|
ESC16-00015
| DOC - Permit Finaled | 7/27/2016 | 7/27/2016 | 7/27/2016 12:56:54 PM | P | PASS |
|
|
Home complete, landscaped/stabilized. Temp BMPs to remain while active SFHs are still in progress by Tahoe in Belmar.
|
ESC15-00957
| General Inspection | 7/27/2016 | 7/27/2016 | 7/27/2016 12:55:17 PM | | PASS |
|
|
WIP on SFHs by Tahoe and Z. Evans Construction. Two concrete washouts provided, no areas of significant trackout . Sites have trash containment and are relatively clean/well kept. Storm drains fitted with sediment filter bags.
|
ESC16-00018
| DOC - Permit Finaled | 7/27/2016 | 7/27/2016 | 7/27/2016 12:51:27 PM | P | PASS |
|
|
Home complete, landscaped/stabilized. Temp BMPs to remain while active SFHs are still in progress by Tahoe in Belmar.
|
ESC15-01227
| General Inspection | 7/27/2016 | 7/27/2016 | 7/27/2016 12:28:22 PM | | CANC |
|
|
|
ESC16-00876
| BMP Violation | 7/25/2016 | 7/27/2016 | 7/27/2016 12:22:35 PM | A | PART |
|
|
sweep up request follow-up
Initial cement dust was swept and cleaned as well sediment. Driveway appears to have just been poured with some more concrete material left in gutter. Need to sweep up again today when the driveway dries.
|
ESC16-00783
| Site Preparation | 7/26/2016 | 7/27/2016 | 7/27/2016 11:59:55 AM | A | PASS |
|
|
Brett Phone #: ###-####
|
ESC15-00871
| BMP Violation | 7/27/2016 | 7/27/2016 | 7/27/2016 11:50:38 AM | A | CANC |
|
|
data entry error, should be for 7/28
|
ESC15-00871
| General Inspection | 7/27/2016 | 7/27/2016 | 7/27/2016 11:49:37 AM | | FAIL |
|
|
Loose sediment, dirt, gravel and unprotected stockpiles stored on pavement with potential to runoff site with stormwater. No housekeeping has occured this week.
Verbal CN to Chad to have hard surfaces swept, in particular the sidewalk and gutter on Preece.
RP stated it will be swept and cleaned tonight. Follow up inspection scheduled for tommorrow
|
ESC16-00873
| Site Preparation | 7/26/2016 | 7/27/2016 | 7/27/2016 11:26:27 AM | A | PASS |
|
|
Andy-please call 30 minutes prior to meet Phone #: ###-####
Permits on site. Flat lot, no MS4 inlets on Etheridge. RP to monitor housekeeping as main BMP. Approved for construction.
|
ESC16-00874
| Site Preparation | 7/26/2016 | 7/27/2016 | 7/27/2016 11:26:10 AM | A | PASS |
|
|
Andy-please call 30 minutes prior to meet Phone #: ###-####
Permits on site. Flat lot, no MS4 inlets on Etheridge. RP to monitor housekeeping as main BMP. Approved for construction.
|
ESC16-00405
| General Inspection | 7/27/2016 | 7/27/2016 | 7/27/2016 10:52:37 AM | P | PASS |
|
|
Emerald village road base work and sidewalk base work is in progress. SWPPP & Boise ESC permit onsite. Water truck on site for dust control, not in use at time of inspection. No plumes leaving work area/no complaints received. DIs have sediment bags installed and in good condition. No trackout to Curtis or Emerald. No corrections requested.
|
ESC15-01603
| Aging Inspection | 7/27/2016 | 7/27/2016 | 7/27/2016 9:56:52 AM | | PASS |
|
|
|
ESC15-01225
| General Inspection | 7/27/2016 | 7/27/2016 | 7/27/2016 9:55:57 AM | | CANC |
|
|
|
ESC15-01602
| Aging Inspection | 7/27/2016 | 7/27/2016 | 7/27/2016 9:30:57 AM | | PASS |
|
|
|
ESC15-01601
| Aging Inspection | 7/27/2016 | 7/27/2016 | 7/27/2016 9:08:00 AM | | PASS |
|
|
|
ESC15-01161
| General Inspection | 7/27/2016 | 7/27/2016 | 7/27/2016 8:28:36 AM | | PASS |
|
|
BMPs installed. Receiving DI recently cleaned. No discharges or sediment runoff occuring. SFH near completion.
|