MEC00-02326
| Rough-in | 7/27/2000 | 7/28/2000 | 7/28/2000 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 07/27/2000 at 10:16:48. Contact: ###-####. insul r/a attic..connect bath exhaust 7/28/00 8:42:14 AM
|
MEC00-02326
| Pressure Test | 7/27/2000 | 7/28/2000 | 7/28/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/27/2000 at 10:17:30. Contact: ###-####.
|
MEC00-02528
| Rough-in | 7/27/2000 | 7/28/2000 | 7/28/2000 12:00:00 AM | A | FAIL |
|
|
JOE---###-#### FOR F/P covered by a load of sheetrock..no access 7/28/00 8:48:04 AM
|
MEC00-02515
| Rough-in | 7/27/2000 | 7/28/2000 | 7/28/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/27/2000 at 11:55:15. Contact: ###-####.
|
MEC00-02463
| Rough-in | 7/27/2000 | 7/28/2000 | 7/28/2000 12:00:00 AM | A | CANC |
|
|
###-####-TEJANO R/I not enought time..will do mon am 7/28/00 9:54:31 AM
|
MEC00-02494
| Rough-in | 7/27/2000 | 7/28/2000 | 7/28/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/27/2000 at 12:55:19. Contact: ###-####.
|
MEC00-02485
| Final | 7/27/2000 | 7/28/2000 | 7/28/2000 12:00:00 AM | A | FAIL |
|
|
megan ###-#### complete framing and call for reinsp 7/28/00 8:41:51 AM
|
MEC00-02533
| Rough-in | 7/27/2000 | 7/28/2000 | 7/28/2000 12:00:00 AM | A | PASS |
|
|
###-#### r/i-ed hole in r/a...fir out wall at b-vent 2nd story 7/28/00 8:27:38 AM
|
MEC00-02533
| Pressure Test | 7/27/2000 | 7/28/2000 | 7/28/2000 12:00:00 AM | A | PASS |
|
|
ed ###-#### pres test
|
MEC00-01870
| Final | 7/27/2000 | 7/28/2000 | 7/28/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/27/2000 at 15:43:29. Contact: ###-####.
|
MEC99-00812
| Final | 7/27/2000 | 7/28/2000 | 7/28/2000 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 07/27/2000 at 17:53:26. Contact: ###-####. put sealer on kit floor..no access 7/28/00 9:12:53 AM
|