Inspections for the day of: Tuesday, July 28, 2015.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC14-00865 General Inspection7/28/20157/28/20157/29/2015 11:55:46 AM PASS
WIP on painting Spectrum renovated buildings. New landscaping, curbing, and earthwork is complete. Will need to clean up staging area and remove DI bags in parking lot before closing permit. No corrections at this time.
ESC13-01159 General Inspection7/24/20157/28/20157/29/2015 11:53:09 AMAPEND
Corrections needed:

1. Post SWPPP and City of Boise ESC permit sign.
2. Install perimeter wattles at Heritage and Hiawatha after sweeping up loose dirt
3. Check and service all DI bags
4. Submit updated SWPPP and change permit responsibility if Trilogy is handing over CGP to CBH

ESC13-00520 General Inspection7/28/20157/28/20157/28/2015 4:35:27 PM CANC
ESC13-00707 General Inspection7/28/20157/28/20157/28/2015 4:35:09 PM CANC
ESC14-01063 General Inspection7/28/20157/28/20157/28/2015 4:34:57 PM PART
Work still needs to be done to clean up Bent Bow. All inlets need to be emptied, only about 50% were serviced. WIP on corrections. No new corrections.
ESC14-01120 Site Final7/28/20157/28/20157/28/2015 3:30:46 PMPPASS
Home complete, landscaped, and occupied. No loose sediment leaving site, no building materials. ESC permit finaled.
ESC15-00882 Random Inspection7/28/20157/28/20157/28/2015 3:14:38 PMPFAIL
No discharges or significant track out but work has started without BMPs installed.

Verbal Correction request to RP M. Jobes to install DI bag and perimeter wattles.
ESC15-00957 Site Preparation7/28/20157/28/20157/28/2015 3:06:14 PMPPASS
Permit sign posted at entrance, SWPPP and NOI onsite.

Some initial grubbing and outbuilding demolition has occured. No fugitive dust observed. Initial BMPs installed. Will need to add material storage area and concrete washout for curb work.

Approved to excavate.
ESC15-00851 General Inspection7/28/20157/28/20157/28/2015 10:40:11 AMAPASS
Ann Morrison soccer field re-grading and turf installation is in progress. Turf from Basque friendly is now on Field #3 and is surrounded by security fence and already inhabited by geese. A stockpile of sand in adjacent parking lot should be removed and area swept.

Now Precision grading is working on leveling #4. No trackout from work entrance, no fugitive dust issues, permit sign is posted.

Approved.
ESC15-00957 Site Preparation7/27/20157/28/20157/28/2015 10:25:45 AMAPEND
re-scheduled for PM ride-along
ESC14-00438 General Inspection7/28/20157/28/20157/28/2015 8:58:49 AM PASS