Inspections for the day of: Tuesday, July 28, 2020.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTell Riley
TitleBLD-COM/RES INSPECTOR
Phone #830-2752
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-00362 BLD-Final7/27/20207/28/20207/28/2020 5:46:38 PMAPART
Screened- Troy Phone #: ###-####/temp occupancy ok, see entry from zoning, see email to Troy for public works--other signatures are on card// will need final special inspection report prior to permanant occupancy//
BLD20-01853 BLD-Foundation7/28/20207/28/20207/28/2020 5:45:07 PMPNR
Screened- Cameron Phone #: ###-####/7035706//rebar needs to be installed per the engineering alternate detail// a knife plate will be post installed into the pier//
BLD20-00219 BLD-Final7/28/20207/28/20207/28/2020 3:53:58 PMPNR
Phone #: ###-#### Inspection requested via web by Ted Perry//need zoning and fire life safety finals prior to building final//
BLD20-02185 BLD-Wall cover7/28/20207/28/20207/28/2020 3:34:57 PMPCANC
Justin *screened* Phone #: ###-####//electrical failed will need to reschedule//
BLD20-02499 BLD-Final7/27/20207/28/20207/28/2020 3:03:18 PMPPASS
Thank you! Phone #: ###-#### Inspection requested via web by Dale Hope
BLD20-02499 DOC - Permit Finaled7/28/20207/28/20207/28/2020 3:03:08 PMPPASS
BLD20-01397 BLD-Framing/Rough-in7/28/20207/28/20207/28/2020 2:27:38 PMPFAIL
Gabe *screened* Phone #: ###-####//engineering provided for fix of trusses modified for pitch change--the engineering fix has not been completed onsite, the fix needs to reflect the approved engineering fix//let Gabe know//
BLD20-00223 BLD-Conference7/28/20207/28/20207/28/2020 1:44:08 PMPCANC
Screened // Robert Phone #: ###-####
BLD20-00223 BLD-Final7/28/20207/28/20207/28/2020 1:43:58 PMPPASS
ok when furnace conduit is sealed at the separation wall in garage--let contractor know//
BLD20-00223 DOC - Permit Finaled7/28/20207/28/20207/28/2020 1:43:22 PMPPASS
BLD19-04773 BLD-Energy code compliance7/28/20207/28/20207/28/2020 11:30:02 AMAPART
Final Framing/ Energy

Please call 30 minutes prior Phone #: ###-#### Inspection requested via web by Shane Shade//minor corrections, ok to hang separation wall will need to check for shear nailing//
BLD19-04772 BLD-Energy code compliance7/28/20207/28/20207/28/2020 11:29:45 AMAPART
Final Framing/Energy Phone #: ###-#### Inspection requested via web by Shane Shade//minor corrections, ok to hang separation wall will need to check for shear nailing//
BLD19-04770 BLD-Energy code compliance7/28/20207/28/20207/28/2020 11:29:30 AMAPART
Final Framing/ Energy Phone #: ###-#### Inspection requested via web by Shane Shade//minor corrections, ok to hang separation wall will need to check for shear nailing//
BLD19-04767 BLD-Energy code compliance7/28/20207/28/20207/28/2020 11:29:14 AMAPART
Final Framing/Energy Phone #: ###-#### Inspection requested via web by Shane Shade//minor corrections, ok to hang separation wall will need to check for shear nailing//
BLD20-01857 BLD-Final7/27/20207/28/20207/28/2020 11:19:40 AMAPASS
Per the inspector: No one needs to be there. The homeowner is DEAF so they will not hear you if you knock on the door. Please text ###-#### and they can come out, but I also asked them to leave a note on the gate or front door granting you access.
If you have any questions about the inspection, or need one of our representatives, please call our tech Mierins at ###-#### Phone #: ###-#### Inspection requested via web by BRS Permitting//ok per approved plans//
BLD20-01857 DOC - Permit Finaled7/28/20207/28/20207/28/2020 11:19:19 AMPPASS
BLD18-01475 BLD-Final7/27/20207/28/20207/28/2020 10:09:58 AMAFAIL
Joe - */Screened*/ Phone #: ###-####//see CN left with Joe for framing, alarms and landscaping// part of deck is existing, including the escape window and grate, part of original deck//
BLD20-02355 BLD-Final7/27/20207/28/20207/28/2020 9:14:38 AMAPASS
Inspection requested via web by Hans Weikl
BLD20-02355 DOC - Permit Finaled7/28/20207/28/20207/28/2020 9:14:21 AMPPASS
roof appears to be installed within code requirements//ridge vents installed and new flashings installed//