BLD02-00527
| BLD-Framing/Rough-in | 7/26/2002 | 7/29/2002 | 7/29/2002 12:00:00 AM | | CANC |
|
|
ROGER ###-#### by rodger 7/29/2002 10:59:01 AM
|
BLD02-00595
| BLD-Final | 7/26/2002 | 7/29/2002 | 7/29/2002 12:00:00 AM | A | PART |
|
|
jeremy; Phone #: ###-#### bathrooms behind eleavator shaft not complete 7/29/2002 2:19:19 PM
|
BLD02-01051
| BLD-Final | 7/26/2002 | 7/29/2002 | 7/29/2002 12:00:00 AM | A | NH |
|
|
Scheduled by a contractor via Hello! on 07/26/2002 at 16:10:42. Contact: ###-####. unable to get in back yard 7/29/2002 9:23:43 AM
|
BLD02-00732
| BLD-Framing/Rough-in | 7/25/2002 | 7/29/2002 | 7/29/2002 12:00:00 AM | A | PART |
|
|
MIKE; Phone #: ###-#### ok to cover steel int studs 7/29/2002 10:53:39 AM
|
BLD02-01752
| BLD-Footing | 7/26/2002 | 7/29/2002 | 7/29/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 07/26/2002 at 11:33:19. Contact: ###-####.
|
BLD02-00591
| BLD-Final | 7/26/2002 | 7/29/2002 | 7/29/2002 12:00:00 AM | P | FAIL |
|
|
###-#### needs handrail at new rear porch then ok for lc 7/29/2002 2:39:11 PM
|
BLD02-00820
| BLD-Conference | 7/29/2002 | 7/29/2002 | 7/29/2002 12:00:00 AM | P | PASS |
|
|
handrail consult ###-#### chris
|
BLD02-00305
| BLD-Energy code compliance | 7/29/2002 | 7/29/2002 | 7/29/2002 12:00:00 AM | P | CANC |
|
|
###-#### BRYAN
|
BLD01-02790
| BLD-Framing/Rough-in | 7/29/2002 | 7/29/2002 | 7/29/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 07/29/2002 at 11:23:20. Contact: ###-####. ok to side and roof 7/29/2002 3:15:28 PM 7/29/2002 3:15:47 PM
|
BLD02-01374
| BLD-Framing/Rough-in | 7/29/2002 | 7/29/2002 | 7/29/2002 12:00:00 AM | P | PART |
|
|
CEILING ###-#### RICHARD grid ok 7/29/2002 3:30:05 PM
|