FIR10-00314
| INSP-Final Inspection | 7/29/2010 | 7/29/2010 | 7/29/2010 4:08:07 PM | P | PASS |
|
|
Final inspection passed. Fire sprinkler permit finaled.
|
BLD10-00880
| FIRE-Final Inspection | 7/29/2010 | 7/29/2010 | 7/29/2010 4:06:37 PM | P | PASS |
|
|
Fire life safety passed inspection. One additional fire extinguisher to be posted as discussed.
|
BLD10-01491
| FIRE-Conference | 7/29/2010 | 7/29/2010 | 7/29/2010 4:04:54 PM | A | DONE |
|
|
Regarding existing dampers.
|
FIR10-00258
| INSP-Sprinkler Rough-in/Hydro | 7/29/2010 | 7/29/2010 | 7/29/2010 4:03:58 PM | A | PART |
|
|
Ref. stamped plans on site for inspection notes at the overhead install.
|
FIR10-00295
| INSP-Sprinkler Rough-in/Hydro | 7/29/2010 | 7/29/2010 | 7/29/2010 4:03:02 PM | A | PART |
|
|
1st floor lobby okayed for cover.
|
FIR10-00054
| INSP-Sprinkler Rough-in/Hydro | 7/29/2010 | 7/29/2010 | 7/29/2010 4:02:01 PM | A | PART |
|
|
Okayed for cover at areas per activity notes and annotations on the stamped plans.
|