FIR00-00583
| FIR-Aging Inspection | 7/3/2003 | 7/3/2003 | 7/3/2003 12:00:00 AM | | PASS |
|
|
Finaled by inspector 406 on 6/21/2001 7/3/2003 1:01:51 PM
|
BLD02-01924
| FIRE-Final Inspection | 7/2/2003 | 7/3/2003 | 7/3/2003 12:00:00 AM | A | PASS |
|
|
life safety finaled 7/2/2003 2:47:38 PM
|
FIR02-00459
| INSP-Supply line flush | 7/2/2003 | 7/3/2003 | 7/3/2003 12:00:00 AM | A | PASS |
|
|
Supply line flush is OK 7/3/2003 12:29:30 PM
|
BLD01-01537
| BLD-Final | 7/2/2003 | 7/3/2003 | 7/3/2003 12:00:00 AM | A | PART |
|
|
Temp given for grading and drainage permit. Sign off was for phase 1A. 7/2/2003 2:51:10 PM
|
FIR03-00251
| INSP-Sprinkler Rough-in/Hydro | 7/3/2003 | 7/3/2003 | 7/3/2003 12:00:00 AM | A | FAIL |
|
|
Sprinkler upright is spaced more than 7'-6" off the office wall. Sprinkler riser needs inspected still. 7/3/2003 12:36:27 PM
|
FIR02-00432
| INSP-Final Inspection | 7/2/2003 | 7/3/2003 | 7/3/2003 12:00:00 AM | P | FAIL |
|
|
Project not ready for a final inspection yet. Underground supply flush was OK though 7/3/2003 4:06:59 PM
|
FIR02-00459
| INSP-Sprinkler Rough-in/Hydro | 7/3/2003 | 7/3/2003 | 7/3/2003 12:00:00 AM | P | PART |
|
|
items on the approved plans have been corrected in areas "C" and "D". Sprinkler rough-in in area "A" and "B" is OK
|
FIR03-00251
| INSP-Sprinkler Rough-in/Hydro | 7/3/2003 | 7/3/2003 | 7/3/2003 12:00:00 AM | P | PASS |
|
|
Underground supply line hydro is ok
|
BLD03-00301
| FIRE-Final Inspection | 7/3/2003 | 7/3/2003 | 7/3/2003 12:00:00 AM | P | PASS |
|
|
Fire alarm, fire sprinkler and fire life safety finaled. Fire alarm system is complete
|
BLD02-02390
| FIRE-Final Inspection | 7/3/2003 | 7/3/2003 | 7/3/2003 12:00:00 AM | P | PASS |
|
|
Fire alarm, fire sprinkler and fire life safety finaled. Fire alarm system is complete
|