Inspections for the day of: Tuesday, July 3, 2007.
Number of inspections: 15
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00940 INSP-Sprinkler Rough-in7/2/20077/3/20077/3/2007 4:08:54 PMPCANC
Rescheduled.
FIR06-00959 INSP-Sprinkler Rough-in7/2/20077/3/20077/3/2007 4:08:24 PMPDEFR
Inspection rescheduled per conversation with contractor.
FIR07-00269 INSP-Final Inspection7/2/20077/3/20077/3/2007 4:07:35 PMPPASS
Fire alarm work passed field testing, permit finaled.
FIR07-00399 INSP-Final Inspection7/2/20077/3/20077/3/2007 4:05:28 PMAPART
TI fire alarm work tested satisfactory, final pending shell alarm permit final, notification at the basement storage area may need adjustment due to caged storage configuration under construction.
FIR07-00398 INSP-Alarm Testing7/2/20077/3/20077/3/2007 4:02:59 PMAPART
Tested FACP, SD and pull station at panel, all fire sprinkler supervision, need resubmittals for all added FS devices not shown on plans, no testing for the elevator or core a/v's as this work is not completed at this time.
BLD06-00845 FIRE-Conference7/2/20077/3/20077/3/2007 3:59:26 PMANR
Need most recent plans for review.
BLD06-03634 FIRE-Final Inspection7/2/20077/3/20077/3/2007 3:58:27 PMANR
Pending shell related permit finals.
FIR07-00342 INSP-Final Inspection7/2/20077/3/20077/3/2007 3:50:00 PMAPART
Final pending building shell and core permit finals.
FIR06-00727 INSP-Sprinkler Rough-in/Hydro6/29/20077/3/20077/3/2007 12:37:25 PMAPART
OH hydrostatic testing for the attic dry system completed okay, remainder of the dry system rough-in failed due lacking coverage at the east side of the elevator shaft, two uprights at the west end are installed too low, one plugged outlet needs to be rotated to avoid water collection and freeze potential, items from previous inspection have been corrected.
BLD06-00628 FIRE-Final Inspection7/2/20077/3/20077/3/2007 12:13:00 PMAPASS
Corrections verified, shell fire life safety inspection passed.
BLD07-00064 FIRE-Conference7/2/20077/3/20077/3/2007 11:37:56 AMADONE
On site conference to discuss project related life safety issues and the three hood suppression systems.
BLD06-03177 FIRE-Final Inspection7/2/20077/3/20077/3/2007 10:37:54 AMAPASS
Fire life safety final inspection passed.
FIR07-00203 INSP-Sprinkler Rough-in/Hydro7/2/20077/3/20077/3/2007 10:06:15 AMACANC
24 hour air test for 6" dry system. Phone #: ###-#### Internet Inspection Request from: Jeff Packham
FIR07-00244 INSP-Final Inspection7/2/20077/3/20077/3/2007 10:00:43 AMAFAIL
Not all corrections noted at the previous inspection are finished, still missing retaining straps at two locations (server room 221, janitors 203), the copy room and restrooms are not completed, missing coverage outside the common corridor at the north side for shell protection-see approved plans for location.
FIR07-00357 INSP-Final Inspection7/2/20077/3/20077/3/2007 9:54:52 AMAPART
Corrections verified for completion, OH rough-in is approved for cover at the drop ceilings.