ESC14-00366
| General Inspection | 7/30/2014 | 7/30/2014 | 7/30/2014 1:04:20 PM | | PASS |
|
|
Interior demolition in progress. Staging area is in parking lot to the east of building. There is ACHD work also occuring in the alley behind building to install permeable asphalt for LID stormwater management.
No violations observed.
|
ESC14-00162
| Complaint Inspection | 7/30/2014 | 7/30/2014 | 7/30/2014 11:18:33 AM | A | PART |
|
|
No activity at site at time of inspection.
Observations: 1. Site is in decent condition. Permit posted, trash is contained, no illicit discharges, and concrete and liquid waste washout provided in backyard. 2. Need to sweep sidewalk, top of curb, and gutter in front of house. In addition to tree litter, there is also sand, sediment, and pebbles from construction activity that have accumulated. 3. The porta-pot is quite close to neighbor's back porch and grill area. Called A-company and requested that it be relocated next to detached garage and alley. They said they could schedule it this week despite just being serviced last week. It is on a 2 week cleaning schedule 7/23 and again next Wednesday. There was not excessive odor or leakage.
Written CN to sweep as mentioned above posted on site.
|
ESC13-01054
| Aging Inspection | 7/30/2014 | 7/30/2014 | 7/30/2014 10:47:17 AM | | PASS |
|
|
Most exterior work is complete. Yard is not yet landscaped/stabilized. No violations observed.
|
ESC14-00239
| General Inspection | 7/30/2014 | 7/30/2014 | 7/30/2014 10:33:48 AM | | PART |
|
|
Sherwood Apts. in the Lusk district is working on first floor. All surrounding DI's have protection. At the moment there is utility work and road patching occuring so trackout is hard to assess.
No discharges, excessive dust observed.
Correction:
When road work is complete, the gutters around the site should be swept to remove sediment and gravel that has collected.
|
ESC14-00212
| General Inspection | 7/30/2014 | 7/30/2014 | 7/30/2014 10:28:28 AM | | PASS |
|
|
Lusk Place has about 2-3 more weeks of work until footings are complete and dewatering may cease. Currently there are 2 dewatering pumps connected to a hose with the capabilitiy to run through the a sediment filtration tank. The hose is not connected to the tank because the pH and turbidity are within the water quality standards. I visually checked the outlet for clearness and erosion at the outlet splash zone. McAlvain RP Jose has a log daily water quality measurments.
BMPs are working and regular street is being performed. A water truck was in use on site for dust suppression.
In compliance.
|
ESC14-00333
| General Inspection | 7/30/2014 | 7/30/2014 | 7/30/2014 9:32:44 AM | | PASS |
|
|
Ranch Market frame is now being erected. The fuel tanks and utilities have already been installed.
Permit is posted, construction entrance in good condition, concrete washout is provided. No sediment or discharges leaving the site.
Approved.
|
ESC12-00539
| General Inspection | 7/30/2014 | 7/30/2014 | 7/30/2014 9:16:11 AM | | PASS |
|
|
Some stockpiles remain in between DH Estates #9 and #12 which may need to be removed per this permit if not the DH#12 permit. DH #8 is finished with no open parcels remaining.
No corrections needed at this time.
|
ESC13-00791
| Aging Inspection | 7/30/2014 | 7/30/2014 | 7/30/2014 9:11:26 AM | | PASS |
|
|
Finaled.
|
ESC13-00791
| DOC - Permit Finaled | 7/30/2014 | 7/30/2014 | 7/30/2014 9:11:14 AM | P | PASS |
|
|
Home is complete, landscaped, and occupied. ESC conditions satisfied.
|
ESC13-00954
| Aging Inspection | 7/30/2014 | 7/30/2014 | 7/30/2014 8:42:12 AM | | PASS |
|
|
Finaled.
|
ESC13-00954
| DOC - Permit Finaled | 7/30/2014 | 7/30/2014 | 7/30/2014 8:41:42 AM | P | PASS |
|
|
Project complete and landscaped. Area in front and back of house is stabilized and construction materials and dirt have been swept. ESC conditions satisfied.
|