BLD15-02391
| FIRE-Final Inspection | 7/30/2015 | 7/30/2015 | 7/30/2015 3:28:28 PM | P | FAIL |
|
|
Met with Erin and found that they are not quite ready yet. I rescheduled for tomorrow morning.
|
FIR15-00504
| INSP-Sprinkler Rough-in/Hydro | 7/30/2015 | 7/30/2015 | 7/30/2015 3:00:10 PM | P | PASS |
|
|
Combustible concealed space has been filled with insulation. Piping can be covered. Also the earthquake bracing has been completed.
|
BLD15-02289
| FIRE-Final Inspection | 7/29/2015 | 7/30/2015 | 7/30/2015 2:58:30 PM | A | FAIL |
|
|
Repair the exit signs at the front and rear exit doors.
|
FIR15-00220
| INSP-Supply line flush | 7/30/2015 | 7/30/2015 | 7/30/2015 2:11:56 PM | P | PASS |
|
|
Underground flush passed
|
FIR15-00222
| INSP-Sprinkler Rough-in | 7/29/2015 | 7/30/2015 | 7/30/2015 2:11:14 PM | P | PASS |
|
|
Rough-in and tenting passed. Piping can be covered. Brian and I spoke about the tenting to create a pocket for the piping since in several places the tenting contractor stapled the insulation to the deck. He was going to follow up with Anderson Construction.
|
FIR15-00346
| INSP-Sprinkler Rough-in | 7/29/2015 | 7/30/2015 | 7/30/2015 12:04:25 PM | A | PASS |
|
|
See the city approved plans for ceiling that are ok to cover piping
|
BLD15-00488
| FIRE-Final Inspection | 7/30/2015 | 7/30/2015 | 7/30/2015 9:53:47 AM | P | PASS |
|
|
Life safety passed
|
BLD15-02404
| FIRE-Final Inspection | 7/24/2015 | 7/30/2015 | 7/30/2015 9:49:56 AM | A | FAIL |
|
|
Provide annual inspection for the sprinkler system, provide door hardware, provide sticker at main entrance, provide exit sign at main entrance or permission to delete, provide annual inspection for the fire extinguisher and provide correct suite number.
|
FIR15-00321
| INSP-Sprinkler Rough-in | 7/29/2015 | 7/30/2015 | 7/30/2015 9:31:02 AM | A | PASS |
|
|
The overhead rough to cover and tenting inspection passed. Piping can be covered.
|