Inspections for the day of: Thursday, July 30, 2020.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDave Hannah
TitleBLD-COM/RES INSPECTOR
Phone #794-1967
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MIS19-00206 MIS-Aging Inspection7/30/20207/30/20208/8/2020 8:11:05 AM PART
ok to insulate and put enter shaft walls back to in
BLD20-01365 BLD-Footing7/28/20207/30/20207/31/2020 6:15:03 AMPPEND
jason *screened* Phone #: ###-#### ok after spec inspection sign off
BLD18-03767 BLD-Foundation7/30/20207/30/20207/31/2020 6:14:28 AMPPEND
SCREENED Rebar // Keith Phone #: ###-#### ok after spec inspection siign off
BLD19-03238 BLD-Framing/Rough-in7/29/20207/30/20207/30/2020 5:57:20 PMAPART
Joe Phone #: ###-#### ok steel studs 1st 2nd and 3rd ok mto prerock and insulate
BLD20-02017 BLD-Wall cover7/29/20207/30/20207/30/2020 5:45:08 PMANR
Phone #: ###-#### Inspection requested via web by Nick Schuler
BLD20-02017 BLD-Framing/Rough-in7/29/20207/30/20207/30/2020 5:44:49 PMANR
Minor framing added to make a bedroom and fir some walls out for plumbing etc. Not sure if it needs inspected. If it does please inspect. Phone #: ###-#### Inspection requested via web by Nick Schuler needs trade rough ins
BLD20-01160 BLD-Framing/Rough-in7/30/20207/30/20207/30/2020 5:43:33 PMPNR
Keith - *inspector enteres through seperate door from main property* */Screened*/ Phone #: ###-####
BLD20-00366 BLD-Foundation7/30/20207/30/20207/30/2020 1:19:05 PMPPEND
Masonry/Rebar inpsection request for new gym. Remaining 12 to 16 feet of masonry being grouted at 2pm. MTI scheduled to be on site as well. Please call Dan with any issues. Phone #: ###-#### Inspection requested via web by Dan Koski ok grout after spec inspection aproves
BLD20-02507 BLD-Final7/29/20207/30/20207/30/2020 1:17:57 PMPPASS
Screened- Jill Phone #: ###-####
BLD20-01540 BLD-Framing/Rough-in7/29/20207/30/20207/30/2020 9:40:24 AMAPEND
Don *screened* Phone #: ###-#### ok after elec rought in
BLD20-02455 BLD-Framing/Rough-in7/29/20207/30/20207/30/2020 9:39:55 AMAPASS
Jay Walters is the onsite contact - ###-#### Phone #: ###-#### Inspection requested via web by BRS Permitting