MEC95-00371
| INSP - Final | 7/31/1995 | 7/31/1995 | 7/31/1995 12:00:00 AM | | PASS |
|
|
|
MEC3047726
| INSP - Final | 7/31/1995 | 7/31/1995 | 7/31/1995 12:00:00 AM | A | PASS |
|
|
final ok 20 min
|
MEC95-00046
| INSP - Final | 7/28/1995 | 7/31/1995 | 7/31/1995 12:00:00 AM | A | PASS |
|
|
pipe fixed in crawl. 20 min
|
MEC95-00356
| INSP - Framing/ Rough-in | 7/31/1995 | 7/31/1995 | 7/31/1995 12:00:00 AM | A | PASS |
|
|
corrections were made. 20 min
|
MEC95-00357
| INSP - Framing/ Rough-in | 7/28/1995 | 7/31/1995 | 7/31/1995 12:00:00 AM | A | FAIL |
|
|
r/i and gas test no ready. don't think gas will be done by hvac but by the plumber. 15 min
|
MEC95-00362
| INSP - Framing/ Rough-in | 7/31/1995 | 7/31/1995 | 7/31/1995 12:00:00 AM | A | PASS |
|
|
r/i ok 15 min
|
MEC95-00362
| INSP - Gas pressure test | 7/31/1995 | 7/31/1995 | 7/31/1995 12:00:00 AM | A | PASS |
|
|
gas piping ok #26200 20 min.
|
MEC95-00364
| INSP - Framing/ Rough-in | 7/31/1995 | 7/31/1995 | 7/31/1995 12:00:00 AM | P | FAIL |
|
|
need: draft stop at attic penetration and maintain 1" clearance on bw vent. 20 min
|
MEC95-00364
| INSP - Gas pressure test | 7/31/1995 | 7/31/1995 | 7/31/1995 12:00:00 AM | P | PASS |
|
|
gas piping to wall furnace approved. #26195 15 min.
|
MEC95-00365
| INSP - Gas pressure test | 7/31/1995 | 7/31/1995 | 7/31/1995 12:00:00 AM | P | PASS |
|
|
gas piping to new range ok. #26198 20 min
|
MEC95-00314
| INSP - Gas pressure test | 7/31/1995 | 7/31/1995 | 7/31/1995 12:00:00 AM | P | PASS |
|
|
gas test ok #26196 20 min
|