Inspections for the day of: Wednesday, July 31, 2019.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Story
TitleELE-INSPECTOR
Phone #985-3493
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-02791 Rough-In Permanent Service7/26/20197/31/20197/31/2019 2:37:17 PMPFAIL
Phone #: ###-#### Inspection requested via web by Same Electric
AFC calc required for commercial services
ELE19-01727 Final7/30/20197/31/20197/31/2019 2:20:10 PMPCANC
This is a partial final for temp occupancy permit. Contact is Ryan Weiderich. Phone #: ###-#### Inspection requested via web by Scott Campbell
ELE19-01615 Electrical Rough-In7/31/20197/31/20197/31/2019 1:23:46 PMPPASS
The new building is in the back of the school Phone #: ###-#### Inspection requested via web by robert feller
Walls@hard lids only ok to cover
ELE19-02729 Final7/31/20197/31/20197/31/2019 1:00:47 PMPPASS
Please call when you are on your way to the site. Phone #: ###-#### Inspection requested via web by Spencer McLean
Final ok
ELE19-00747 Final7/30/20197/31/20197/31/2019 11:03:32 AMAPART
Electrical final on Units 120, 121, 122 and 123.
Justin Carbonaro will be on site for access issues. Phone #: ###-#### Inspection requested via web by Tod Lane

Units as requested ok
ELE19-01016 Final7/30/20197/31/20197/31/2019 10:16:28 AMAPASS
Phone #: ###-#### Inspection requested via web by Lee VanSchoiack
Occ card signed Final ok

ELE19-02841 Electrical Rough-In7/30/20197/31/20197/31/2019 9:32:01 AMAPASS
Electrical rough in please. Thank you. Have a bless day! Phone #: ###-#### Inspection requested via web by Kyle Lott
Upstairs area ok to cover. No floor outlet at this time until they decide to change area to conference room in the future...
ELE18-04829 Final7/29/20197/31/20197/31/2019 8:18:14 AMAPASS
Phone #: ###-#### Inspection requested via web by Laurie Hoelscher
Sign final ok