Inspections for the day of: Thursday, July 5, 2007.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR06-00940 INSP-Sprinkler Rough-in7/3/20077/5/20077/5/2007 5:16:39 PMAFAIL
Inspection intended for FIR07-00205, inspected areas C and D on the 2nd level, see sheet FP8 for defficiencies including overspaced heads and blocked heads.
FIR07-00203 INSP-Sprinkler Rough-in/Hydro7/5/20077/5/20077/5/2007 3:33:20 PMPDEFR
Scheduled by a contractor via Hello! on 7/5/2007 at 7:31:03 AM. Contact: ###-####.
FIR07-00034 INSP-Final Inspection7/3/20077/5/20077/5/2007 3:27:27 PMAPASS
Shell fire sprinkler permit is approved for final as noted.
FIR07-00542 INSP-Final Inspection7/5/20077/5/20077/5/2007 2:48:30 PMPPASS
Fire alarm work passed field inspection, permit finaled.
BLD06-02700 FIRE-Final Inspection7/5/20077/5/20077/5/2007 2:47:24 PMPFAIL
Emergency light at the elevator lobby 5th floor failed to function, one fire door at the 3rd floor west side atrium pair failed to close on general alarm, exit sign at the 2nd floor east side does not illuminate on power fail.
BLD06-02700 FIRE-Sprinkler Rough-in7/5/20077/5/20077/5/2007 2:44:07 PMPPASS
Required corrections for the corridor fire sprinklers on the 2nd, 3rd, 4th, and 5th levels completed satisfactory.
FIR07-00234 INSP-Sprinkler Rough-in/Hydro7/3/20077/5/20077/5/2007 1:44:22 PMPFAIL
OH rough-in is not approved for cover until system piping is correctly attatched to the structure as required, missing hangers and upward restraint at several locations, noted some heads have been added and piping relocated from approved plan set, OH hydro test not ready at this time due to pressure loss, tenting appears adequate.
FIR07-00203 INSP-Sprinkler Rough-in/Hydro7/3/20077/5/20077/5/2007 12:44:33 PMAPART
Begin retest of the 24 hr. pneumatic for the roof level dry system at 12:30 pm with 44 1/2 psi at the guage.
FIR06-01010 INSP-Final Inspection7/3/20077/5/20077/5/2007 11:21:49 AMAPASS
UG fire supply line permit finaled.
FIR07-00543 INSP-Sprinkler Rough-in/Hydro7/3/20077/5/20077/3/2007 4:24:49 PMACANC
Phone #: ###-#### Internet Inspection Request from: John Warnick Inspection cancelled from web by: John Warnick