Inspections for the day of: Wednesday, July 5, 2017.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD16-03176 FIRE-Final Inspection7/3/20177/5/20177/5/2017 2:12:05 PMPFAIL
Still missing two exit signs as marked on the city approved plans.
FIR16-00821 INSP-Sprinkler Rough-in7/3/20177/5/20177/5/2017 2:11:18 PMPFAIL
Contact plan review about plan modifications due to additional 90's in the 1 1/2" branchlines that effect the hydraulic calculations. Three branchlines need to be modified for spacing in the trusses and insulation needs to be added in the combustible concealed spaces as discussed. I also noted potential obstructions to the side wall sprinkler heads due to light fixtures. Piping can not be covered yet.
BLD17-00818 FIRE-Final Inspection7/5/20177/5/20177/5/2017 10:42:23 AMPPASS
life safety passed
FIR17-00080 INSP-Sprinkler Rough-in/Hydro6/30/20177/5/20177/5/2017 10:11:33 AMAPASS
System #1 and #2 overhead hydro tests passed
FIR16-00284 INSP-Sprinkler Rough-in7/5/20177/5/20177/5/2017 9:58:45 AMPPASS
Second floor cover for the soffits is ok for cover in the corridor.
BLD17-00302 FIRE-Conference7/3/20177/5/20177/5/2017 9:27:44 AMADONE
Mark and I discussed the removal of an old sprinkler system in the basement. I deferred him to a demo permit. The existing system consists of two upright heads in the mechanical room with a flow switch, alarm bell in the room and a quarter turn valve locked open. The 1" piping is fed from a 3/4" feed. I could not find any old permits for this work and there are no annual inspection tags.