Inspections for the day of: Thursday, July 5, 2018.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-01180 FIRE-Final Inspection7/5/20187/5/20187/6/2018 1:42:59 PMPPASS
Life safety passed

Jack Phone #: ###-####
BLD17-01656 FIRE-Final Inspection7/5/20187/5/20187/6/2018 1:42:34 PMPFAIL
Need plan review approval of the doors being sliding not swinging out of Corridor 105 and that the door hardware is approved on the sliding doors (it requires fingers to open).

Jack Phone #: ###-####
BLD18-01683 FIRE-Final Inspection7/5/20187/5/20187/5/2018 12:59:46 PMPPASS
Life safety passed

Kimberly Phone #: ###-####
BLD18-01572 FIRE-Final Inspection7/5/20187/5/20187/5/2018 11:51:16 AMPPASS
Life safety passed. Contractor is installing single action hardware on the two exit doors.


Tom Phone #: ###-####
FIR18-00457 INSP-Conference7/5/20187/5/20187/5/2018 10:56:27 AMPDONE
It appears that a plan modification will be required due to the changes made.
FIR18-00520 INSP-Final Inspection7/3/20187/5/20187/5/2018 10:55:35 AMPPASS
Permit finaled

Please call Rick with questions Phone #: ###-#### Inspection requested via web by Jeff Packham
NAF17-00091 INSP-Supply line flush7/3/20187/5/20187/5/2018 10:18:38 AMAPASS
Underground flush passed

Please call Troy with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
BLD18-01310 FIRE-Final Inspection7/4/20187/5/20187/5/2018 9:12:02 AMPFAIL
Provide exit sign/emergency light as discussed into the lobby from the training room, provide occupant load signs for both training rooms as per plans, install/provide testing for the access control or resubmit plans deleting this from scope of work, address the electrical panels as noted on the plans.


Please call 15-20 minutes prior to arriving Phone #: ###-#### Inspection requested via web by Colyn Levandoske
FIR18-00442 INSP-Final Inspection7/3/20187/5/20187/5/2018 9:09:18 AMAPASS
Permit finaled
BLD18-01655 FIRE-Final Inspection7/3/20187/5/20187/5/2018 9:07:49 AMAPASS
Life safety passed

Sid Phone #: ###-####
FIR18-00522 INSP-Final Inspection7/3/20187/5/20187/5/2018 9:07:29 AMAPASS
Permit finaled
BLD18-01572 FIRE-Final Inspection7/2/20187/5/20187/5/2018 8:19:07 AMAFAIL
Repair the exit sign in the warehouse and provide single action hardware, as per the plans, for exit doors 2 and 3.

Tom Phone #: ###-####
FIR18-00405 INSP-Final Inspection7/2/20187/5/20187/5/2018 8:18:12 AMAPASS
permit finaled

Phone #: ###-#### Inspection requested via web by Sam Ball
FIR18-00478 INSP-Sprinkler Rough-in7/4/20187/5/20187/5/2018 7:55:19 AMAPASS
Hard lid cover inspection passed. Piping can be covered.