BLD18-01180
| FIRE-Final Inspection | 7/5/2018 | 7/5/2018 | 7/6/2018 1:42:59 PM | P | PASS |
|
|
Life safety passed
Jack Phone #: ###-####
|
BLD17-01656
| FIRE-Final Inspection | 7/5/2018 | 7/5/2018 | 7/6/2018 1:42:34 PM | P | FAIL |
|
|
Need plan review approval of the doors being sliding not swinging out of Corridor 105 and that the door hardware is approved on the sliding doors (it requires fingers to open).
Jack Phone #: ###-####
|
BLD18-01683
| FIRE-Final Inspection | 7/5/2018 | 7/5/2018 | 7/5/2018 12:59:46 PM | P | PASS |
|
|
Life safety passed
Kimberly Phone #: ###-####
|
BLD18-01572
| FIRE-Final Inspection | 7/5/2018 | 7/5/2018 | 7/5/2018 11:51:16 AM | P | PASS |
|
|
Life safety passed. Contractor is installing single action hardware on the two exit doors.
Tom Phone #: ###-####
|
FIR18-00457
| INSP-Conference | 7/5/2018 | 7/5/2018 | 7/5/2018 10:56:27 AM | P | DONE |
|
|
It appears that a plan modification will be required due to the changes made.
|
FIR18-00520
| INSP-Final Inspection | 7/3/2018 | 7/5/2018 | 7/5/2018 10:55:35 AM | P | PASS |
|
|
Permit finaled
Please call Rick with questions Phone #: ###-#### Inspection requested via web by Jeff Packham
|
NAF17-00091
| INSP-Supply line flush | 7/3/2018 | 7/5/2018 | 7/5/2018 10:18:38 AM | A | PASS |
|
|
Underground flush passed
Please call Troy with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
BLD18-01310
| FIRE-Final Inspection | 7/4/2018 | 7/5/2018 | 7/5/2018 9:12:02 AM | P | FAIL |
|
|
Provide exit sign/emergency light as discussed into the lobby from the training room, provide occupant load signs for both training rooms as per plans, install/provide testing for the access control or resubmit plans deleting this from scope of work, address the electrical panels as noted on the plans.
Please call 15-20 minutes prior to arriving Phone #: ###-#### Inspection requested via web by Colyn Levandoske
|
FIR18-00442
| INSP-Final Inspection | 7/3/2018 | 7/5/2018 | 7/5/2018 9:09:18 AM | A | PASS |
|
|
Permit finaled
|
BLD18-01655
| FIRE-Final Inspection | 7/3/2018 | 7/5/2018 | 7/5/2018 9:07:49 AM | A | PASS |
|
|
Life safety passed
Sid Phone #: ###-####
|
FIR18-00522
| INSP-Final Inspection | 7/3/2018 | 7/5/2018 | 7/5/2018 9:07:29 AM | A | PASS |
|
|
Permit finaled
|
BLD18-01572
| FIRE-Final Inspection | 7/2/2018 | 7/5/2018 | 7/5/2018 8:19:07 AM | A | FAIL |
|
|
Repair the exit sign in the warehouse and provide single action hardware, as per the plans, for exit doors 2 and 3.
Tom Phone #: ###-####
|
FIR18-00405
| INSP-Final Inspection | 7/2/2018 | 7/5/2018 | 7/5/2018 8:18:12 AM | A | PASS |
|
|
permit finaled
Phone #: ###-#### Inspection requested via web by Sam Ball
|
FIR18-00478
| INSP-Sprinkler Rough-in | 7/4/2018 | 7/5/2018 | 7/5/2018 7:55:19 AM | A | PASS |
|
|
Hard lid cover inspection passed. Piping can be covered.
|